Stochastic Short-Term Hydro-Thermal Scheduling Based on Mixed Integer Programming with Volatile Wind Power Generation

نویسندگان

  • H. Barati Department of Electrical Engineering, Dezful Branch, Islamic Azad University, Dezful, Iran
  • M. Karami Department of Electrical Engineering, Ahvaz Branch, Islamic Azad University, Ahvaz, Iran
  • M. R. Behnamfar Department of Electrical Engineering, Dezful Branch, Islamic Azad University, Dezful, Iran
چکیده مقاله:

This study addresses a stochastic structure for generation companies (GenCoʼs) that participate in hydro-thermal self-scheduling with a wind power plant on short-term scheduling for simultaneous reserve energy and energy market. In stochastic scheduling of HTSS with a wind power plant, in addition to various types of uncertainties such as energy price, spinning /non-spinning reserve prices, uncertainties of RESs, such as output power of the wind power plant are also taken into account. In the proposed framework, mixed-integer non-linear  programming of the HTSS problem is converted into a MIP. Since the objective of the study is to show how GenCosʼ aim to achieve maximum profit, mixed-integer programming is used here. Therefore, to formulate the MIP for the problem of HTSS with a wind power plant in the real-time modeling, some parameters like the impact of valve loading cost (VLC) that are accompanied by linear modeling, are considered. Furthermore, in thermal units, parameters such as prohibited operating zones (POZs) and different  uncertainties  like the energy  price and wind power are included  to formulate the problem more suitably. The point that is worth noting is the use of dynamic ramp rate (DRR). Also, the application of multi-functional curves (L) of hydro plants is considered  when studying  inter-unit scheduling. Finally, the required tests are conducted  on  a modified  IEEE 118-bus system to verify the accuracy and methodology of the proposed method.

برای دانلود باید عضویت طلایی داشته باشید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Large-Scale Stochastic Mixed-Integer Programming Algorithms for Power Generation Scheduling

This chapter presents a stochastic unit commitment model for power systems and revisits parallel decomposition algorithms for these types of models. The model is a two-stage stochastic programming problem with first-stage binary variables and second-stage mixed-binary variables. The here-and-now decision is to find day-ahead schedules for slow thermal power generators. The wait-and-see decision...

متن کامل

Scheduling security constraint unit commitment for power system including stochastic wind power generation

This paper introduces a new approach for scheduling security constraint unit commitment (SCUC) including wind farms. Because of uncertainty in wind power production, we tried to develop a new method for incorporating wind power generation in power plant scheduling. For this, wind power generation modeled with unit commitment in a non-linear optimization problem and simulated by submitting diffe...

متن کامل

wind farm impact on generation adequacy in power systems

در سال های اخیر به دلیل افزایش دمای متوسط کره زمین، بشر به دنبال روش های جایگزین برای تامین توان الکتریکی مورد نیاز خود بوده و همچنین در اکثر نقاط جهان سوزاندن سوخت های فسیلی در نیروگاه های حرارتی به عنوان مهم ترین روش تولید توان الکتریکی مطرح بوده است. به دلیل توجه به مسایل زیست محیطی، استفاده از منابع انرژی تجدید پذیر در سال های اخیر شدت یافته است. نیروگاه های بادی به عنوان یک منبع تولید توان...

15 صفحه اول

Short-term Hydro Scheduling using Integer Programming: Management and Modelling Issues

The scheduling of hydro stations has stochastic, integer, non-linear, and continuous time aspects, with all the approaches described to date making some simplifying assumption about one or other of these aspects. The (integer) unit commitment decision has received relatively little attention, partly because the resulting problem was deemed intractable given the potential gains in efficiency. Ho...

متن کامل

Short Term Hydro Thermal Scheduling Problem: a Review

Operation of a system having both hydro and thermal plants is far more complex and is of much more importance in a modern interconnected power system. The objective of the STHS problem is to optimize the electricity production, considering a short-term planning horizon. This paper presents an extensive review of a short term hydro thermal scheduling problem. The paper demonstrates results of va...

متن کامل

Short Term Hydro-Thermal Scheduling using Artificial Immunue System

Artificial Immune System is applied to determine the optimal hourly schedule of power generation in a hydrothermal system. A multi-reservoir cascaded hydroelectric system with a nonlinear relationship between water discharge rate, net head and power generation is considered. The water transport delay between connected reservoirs is taken into account. The transmission losses are also taken into...

متن کامل

منابع من

با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

ذخیره در منابع من قبلا به منابع من ذحیره شده

{@ msg_add @}


عنوان ژورنال

دوره 8  شماره 3

صفحات  195- 208

تاریخ انتشار 2020-12-01

با دنبال کردن یک ژورنال هنگامی که شماره جدید این ژورنال منتشر می شود به شما از طریق ایمیل اطلاع داده می شود.