Optimization of an energy based bi-objective multi skilled resource investment project scheduling problem

نویسندگان

  • Behrouz Afshar Nadjafi Faculty of Industrial and Mechanical Engineering, Qazvin Branch, Islamic Azad University, Qazvin, Iran
  • Seyed Taghi Akhavan Niaki Department of Industrial Engineering, Sharif University of Technology, P.O. Box 11155-9414 Azadi Ave., Tehran 1458889694 Iran,
  • Shima Javanmard Faculty of Industrial and Mechanical Engineering, Qazvin Branch, Islamic Azad University, Qazvin, Iran
چکیده مقاله:

Growing concern in the management of energy due to the increasing energy costs, has forced managers to optimize the amount of energy required to provide products and services. This research integrates an energy-based resource investment project-scheduling problem (RIP) under a multi-skilled structure of the resources. The proposed energy based multi skilled resource investment problem (EB-MSRIP) consists of a single project with a set of tasks that require several skills to be competed. Each skill could be applied in several levels of efficiency, each including significant energy and implementation costs. Similar to RIPs, in the EB-MSRIP the required levels of skills are considered as decision variables and a bi-objective formulation is proposed for the problem. The first objective of the model minimizes total cost regarding to energy consumption cost and implementation cost of required multi skilled resources, and the second one minimizes the project’s makespan. The epsilon constraint method has been used to validate the developed formulation on several small-size instances. For larger problem instances, as epsilon constraint method fails to obtain a solution, the multi objective ant colony optimization (MOACO) algorithm has been implemented to tackle the problems. The key control parameters of proposed MOACO are tuned within Taguchi method. Computational results in terms of several comparison metrics including MID, DM, NPS and SNS determine notable advantages of proposed MOACO.

برای دانلود باید عضویت طلایی داشته باشید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Using Multi-Objective Particle Swarm Optimization for Bi-objective Multi-Mode Resource-Constrained Project Scheduling Problem

In this paper the multi-mode resource-constrained project scheduling problem with discounted cash flows is considered. Minimizing the makespan and maximization the net present value (NPV) are the two common objectives that have been investigated in the literature. We apply one evolutionary algorithm named multiobjective particle swarm optimization (MOPSO) to find Pareto front solutions. We used...

متن کامل

Modeling and solving multi-skilled resource-constrained project scheduling problem with calendars in fuzzy condition

In this study, we aim to present a new model for the resource-constrained project scheduling problem (RCPSP) considering a working calendar for project members and determined the skill factor of any member using the efficiency concept. For this purpose, the recyclable resources are staff resources where any person with multiple skills can meet the required skills of activities in a given time. ...

متن کامل

An Evolutionary Algorithm Based on a Hybrid Multi-Attribute Decision Making Method for the Multi-Mode Multi-Skilled Resource-constrained Project Scheduling Problem

This paper addresses the multi-mode multi-skilled resource-constrained project scheduling problem. Activities of real world projects often require more than one skill to be accomplished. Besides, in many real-world situations, the resources are multi-skilled workforces. In presence of multi-skilled resources, it is required to determine the combination of workforces assigned to each activity. H...

متن کامل

A Bi-objective Pre-emption Multi-mode Resource Constrained Project Scheduling Problem with due Dates in the Activities

In this paper, a novel mathematical model for a preemption multi-mode multi-objective resource-constrained project scheduling problem with distinct due dates and positive and negative cash flows is presented. Although optimization of bi-objective problems with due dates is an essential feature of real projects, little effort has been made in studying the P-MMRCPSP while due dates are included i...

متن کامل

Optimizing a bi-objective preemptive multi-mode resource constrained project scheduling problem: NSGA-II and MOICA algorithms

The aim of a multi-mode resource-constrained project scheduling problem (MRCPSP) is to assign resource(s) with the restricted capacity to an execution mode of activities by considering relationship constraints, to achieve pre-determined objective(s). These goals vary with managers or decision makers of any organization who should determine suitable objective(s) considering organization strategi...

متن کامل

The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem

This paper presents the formulation and solution of the Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem. The focus of the proposed method is not on finding a single optimal solution, instead on presenting multiple feasible solutions, with cost and duration information to the project manager. The motivation for developing such an approach is due in part to practica...

متن کامل

منابع من

با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

ذخیره در منابع من قبلا به منابع من ذحیره شده

{@ msg_add @}


عنوان ژورنال

دوره 50  شماره 2

صفحات  31- 40

تاریخ انتشار 2018-12-01