Self-Starting Control Chart and Post Signal Diagnostics for Monitoring Project Earned Value Management Indices

Authors

  • Amirhossein Amiri Department of Industrial Engineering, Faculty of Engineering, Shahed University, Tehran, Iran
  • Fatemeh Sogandi Department of Industrial Engineering, Faculty of Engineering, Shahed University, Tehran, Iran
  • S.Meysam Mousavi Department of Industrial Engineering, Faculty of Engineering, Shahed University, Tehran, Iran
Abstract:

Earned value management (EVM) is a well-known approach in a project control system which uses some indices to track schedule and cost performance of a project. In this paper, a new statistical framework based on self-starting monitoring and change point estimation is proposed to monitor correlated EVM indices which are usually auto-correlated over time and non-normally distributed. Also, a new change point estimator is developed to find the real time of change in the indices mean. Furthermore, a new diagnosing method is presented to recognize the deviated mean index. The performance of the proposed methods is evaluated through simulation studies and an illustrative example.  

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

An ex ante control chart for project monitoring using earned duration management observations

In the past few years, there has been an increasing interest in developing project control systems. The primary purpose of such systems is to indicate whether the actual performance is consistent with the baseline and to produce a signal in the case of non-compliance. Recently, researchers have shown an increased interest in monitoring project’s performance indicators, by plotting them on the S...

full text

A Self-starting Control Chart for Simultaneous Monitoring of Mean and Variance of Simple Linear Profiles

In many processes in real practice at the start-up stages the process parameters are not known a priori and there are no initial samples or data for executing Phase I monitoring and estimating the process parameters. In addition, the practitioners are interested in using one control chart instead of two or more for monitoring location and variability of processes. In this paper, we consider a s...

full text

A risk adjusted self-starting Bernoulli CUSUM control chart with dynamic probability control limits

Usually, in monitoring schemes the nominal value of the process parameter is assumed known. However, this assumption is violated owing to costly sampling and lack of data particularly in healthcare systems. On the other hand, applying a fixed control limit for the risk-adjusted Bernoulli chart causes to a variable in-control average run length performance for patient populations with dissimilar...

full text

Estimation of Project Performance Using Earned Value Management and Fuzzy Regression

Earned Value Management is a critical project managementmethodology that evaluates project performance from cost andschedule viewpoints. The novel theoretical framework presented in thispaper estimates future performance of project regarding the past relativeinformation. It benefits from fuzzy regression (FR) models in estimationprocess in order to deal with the vagueness and impreciseness ofre...

full text

Predicting project time and costs using earned value management based on trapezoidal fuzzy numbers

Projects include activities that must be carried out at certain dates, with specified costs and determined qualities in order to satisfy the stakeholders. Project control is one of the most important and widely used issues in project-based organizations and it has attracted a lot of attention. So far, in the field of project control, there have been a lot of research that were done in different...

full text

Setting tolerance limits for statistical project control using earned value management ¬リニ

Project control has been a research topic since decades that attracts both academics and practitioners. Project control systems indicate the direction of change in preliminary planning variables compared with actual performance. In case their current project performance deviates from the planned performance, a warning is indicated by the system in order to take corrective actions. Earned value ...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 11  issue 2

pages  0- 0

publication date 2018-04-01