Regulatory Impacts on Distributed Generation and Upstream Transmission Substation Expansion Planning: A Novel Stochastic Bi-level Model

Authors

  • F. Misaghi Faculty of Electrical and Computer Engineering, Babol Noshirvani University of Technology, Babol, Mazandaran, Iran.
  • M. Jafari-Nokandi Faculty of Electrical and Computer Engineering, Babol Noshirvani University of Technology, Babol, Mazandaran, Iran.
  • T. Barforoushi Faculty of Electrical and Computer Engineering, Babol Noshirvani University of Technology, Babol, Mazandaran, Iran.
Abstract:

In this paper, a novel framework is proposed to study impacts of regulatory incentive on distributed generation (DG) investment in sub-transmission substations, as well as upgrading of upstream transmission substations. Both conventional and wind power technologies are considered here. Investment incentives are fuel cost, firm contracts, capacity payment and investment subsidy relating to wind power. The problem is modelled as a bi-level stochastic optimization problem, where the upper level consists of investor's decisions maximizing its own profit. Both market clearing and decision on upgrading of transmission substation aiming at minimizing the total cost are considered in the lower level. Due to non-convexity of the lower level and impossibility of converting to single level problem (i.e. mathematical programming with equilibrium constraints (MPEC)), an algorithm combing enumeration and mathematical optimization is used to tackle with the non-convexity. For each upgrading strategy of substations, a stochastic MPEC, converted to a mixed integer linear programming (MILP) is solved. The proposed model is examined on a six-bus and an actual network. Numerical studies confirm that the proposed model can be used for analysing investment behaviour of DGs and substation expansion.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

Distributed Generation Expansion Planning Considering Load Growth Uncertainty: A Novel Multi-Period Stochastic Model

Abstract – Distributed generation (DG) technology is known as an efficient solution for applying in distribution system planning (DSP) problems. Load growth uncertainty associated with distribution network is a significant source of uncertainty which highly affects optimal management of DGs. In order to handle this problem, a novel model is proposed in this paper based on DG solution, consideri...

full text

A Fuzzy Multi Objective Programming Model for Power Generation and Transmission Expansion Planning Problem

The increasing consumption of electricity over time forces different countries to establishnew power plants and transmission lines. There are various crisp single-objective mathematicalmodels in the literature for the long-term power generation and transmission expansion planning tohelp the decision makers to make more reasonable decisions. But, in practice, most of the parametersassociated wit...

full text

Substation Expansion Planning Based on BFOA

In recent years, significant research efforts have been devoted to the optimal planning of power systems. Substation Expansion Planning (SEP) as a sub-system of power system planning consists of finding the most economical solution with the optimal location and size of future substations and/or feeders to meet the future demand. The large number of design variables, and combination of discrete ...

full text

A Multistage Decision-Dependent Stochastic Bi-level Programming Approach for Power Generation Investment Expansion Planning

In this paper, we study the long-term power generation investment expansion planing problem under uncertainty. We propose a bilevel optimization model that includes an upper-level multistage stochastic expansion planning problem and a collection of lower-level economic dispatch problem. This model seeks for the optimal sizing and siting for both thermal and wind power units to be built to maxim...

full text

A New Generation Allocation and Expansion Planning Algorithm Including Transmission System Effects

Generation Expansion Planning (GEP) is one of major modules of power system planning studies, normally performed for the nex 10-30 years horizon. The current industrial practices are to find the generation requirements based on a nodal analysis. In this way, the allocations are not determined and subequent studies are required to find the exact locations which as decomposed from the earli...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 13  issue 2

pages  123- 134

publication date 2017-06