Meta heuristic for Minimizing Makespan in a Flow-line Manufacturing Cell with Sequence Dependent Family Setup Times

Authors

  • Behzad Nikjo MSc, Department of industrial engineering, Mazandaran University of Science and Technology, Babol, Iran
  • Javad Rezaeian Assistant Professor, Department of industrial engineering, Mazandaran University of Science and Technology, Babol, Iran
Abstract:

This paper presents a new mathematical model for the problem of scheduling part families and jobs within each part family in a flow line manufacturing cell where the setup times for each family are sequence dependent and it is desired to minimize the maximum completion time of the last job on the last machine (makespan) while processing parts (jobs) in each family together. Gaining an optimal solution for this type of complex problem in large sizes in reasonable computational time using traditional approaches or optimization tools is extremely difficult. A meta-heuristic method based on Simulated Annealing (SA) is proposed to solve the presented model. Based on the computational analyses, the proposed algorithm was found efficient and effective at finding good quality solutions. 

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

meta heuristic for minimizing makespan in a flow-line manufacturing cell with sequence dependent family setup times

this paper presents a new mathematical model for the problem of scheduling part families and jobs within each part family in a flow line manufacturing cell where the setup times for each family are sequence dependent and it is desired to minimize the maximum completion time of the last job on the last machine (makespan) while processing parts (jobs) in each family together. gaining an optimal s...

full text

Minimizing makespan in a flow-line manufacturing cell with sequence dependent family setup times

This paper presents a new mathematical model for the problem of scheduling part families and jobs within each part family in a flow line manufacturing cell where the setup times for each family are sequence dependent and it is desired to minimize the maximum completion time of the last job on the last machine (makespan) while processing parts (jobs) in each family together. Gaining an optimal s...

full text

New scheduling rules for a dynamic flexible flow line problem with sequence-dependent setup times

In the literature, the application of multi-objective dynamic scheduling problem and simple priority rules are widely studied. Although these rules are not efficient enough due to simplicity and lack of general insight, composite dispatching rules have a very suitable performance because they result from experiments. In this paper, a dynamic flexible flow line problem with sequence-dependent se...

full text

Minimizing the maximum tardiness and makespan criteria in a job shop scheduling problem with sequence dependent setup times

The job shop scheduling problem (JSP) is one of the most difficult problems in traditional scheduling because any job consists of a set operations and also any operation processes by a machine. Whereas the operation is placed in the machine, it is essential to be considering setup times that the times strongly depend on the various sequencing of jobs on the machines. This research is developed ...

full text

Minimizing the total tardiness and makespan in an open shop scheduling problem with sequence-dependent setup times

We consider an open shop scheduling problem with setup and processing times separately such that not only the setup times are dependent on the machines, but also they are dependent on the sequence of jobs that should be processed on a machine. A novel bi-objective mathematical programming is designed in order to minimize the total tardiness and the makespan. Among several mult...

full text

Metaheuristics for scheduling a non-permutation flowline manufacturing cell with sequence dependent family setup times

The broad applications of cellular manufacturing make flowline manufacturing cell scheduling problems with sequence dependent family setup times a core topic in the field of scheduling. Due to computational complexity, almost all published studies focus on using permutation schedules to deal with this problem. To explore the potential effectiveness of treating this argument using non-permutatio...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 7  issue 16

pages  21- 29

publication date 2014-12-01