Heuristic approach to solve hybrid flow shop scheduling problem with unrelated parallel machines

author

Abstract:

In hybrid flow shop scheduling problem (HFS) with unrelated parallel machines, a set of n jobs are processed on k machines. A mixed integer linear programming (MILP) model for the HFS scheduling problems with unrelated parallel machines has been proposed to minimize the maximum completion time (makespan). Since the problem is shown to be NP-complete, it is necessary to use heuristic methods to tackle the moderate to large scale problems. This article presents a new bottleneck-based heuristic to solve the problem. To improve the performance of the heuristic method, a local search approach is embedded in the structure of the heuristic method. To evaluate the performance of the proposed heuristic method, a new lower bound is developed based on Kurz and Askin [1] lower bound. For evaluation purposes, two series of test problems, small and large size problems, are generated under different production scenarios.  The empirical results show that average difference between lower bound and optimal solution as well as lower bound and heuristic method are equal to 2.56% and 5.23%, respectively. For more investigation, the proposed heuristic method is compared by other well-known heuristics in the literature. The results verify the efficiency of the proposed heuristic method in term of number of best solution.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

bicriteria scheduling in hybrid flow shop with unrelated parallel machines

this study considers scheduling in hybrid flow shop environment with unrelated parallel machines for minimizing mean of job's tardiness and mean of job's completion times. this problem does not study in the literature, so far. flexible flow shop environment is applicable in various industries such as wire and spring manufacturing, electronic industries and production lines. after mode...

full text

A hybrid heuristic to solve the parallel machines job-shop scheduling problem

This paper presents an advanced software system for solving the flexible manufacturing systems (FMS) scheduling in a job-shop environment with routing flexibility, where the assignment of operations to identical parallel machines has to be managed, in addition to the traditional sequencing problem. Two of the most promising heuristics from nature for a wide class of combinatorial optimization p...

full text

A New Lower Bound for Flexible Flow Shop Problem with Unrelated Parallel Machines

Flexible flow shop scheduling problem (FFS) with unrelated parallel machines contains sequencing in flow shop where, at any stage, there exists one or more processors. The objective consists of minimizing the maximum completion time. Because of NP-completeness of FFS problem, it is necessary to use heuristics method to address problems of moderate to large scale problem. Therefore, for assessme...

full text

A meta-heuristic approach to solve a JIT scheduling problem in hybrid flow shop

In this paper we address a hybrid flow shop scheduling problem considering the minimization of the sum of the total earliness and tardiness penalties. This problem is proven to be NP-hard, and consequently the development of heuristic and meta-heuristic approaches to solve it is well justified. So, we propose an ant colony optimization method to deal with this problem. Our proposed method has s...

full text

Solving the Problem of Scheduling Unrelated Parallel Machines with Limited Access to Jobs

Nowadays, by successful application of on time production concept in other concepts like production management and storage, the need to complete the processing of jobs in their delivery time is considered a key issue in industrial environments. Unrelated parallel machines scheduling is a general mood of classic problems of parallel machines. In some of the applications of unrelated parallel mac...

full text

A comparison of algorithms for minimizing the sum of earliness and tardiness in hybrid flow-shop scheduling problem with unrelated parallel machines and sequence-dependent setup times

In this paper, the flow-shop scheduling problem with unrelated parallel machines at each stage as well as sequence-dependent setup times under minimization of the sum of earliness and tardiness are studied. The processing times, setup times and due-dates are known in advance. To solve the problem, we introduce a hybrid memetic algorithm as well as a particle swarm optimization algorithm combine...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 28  issue 1

pages  61- 74

publication date 2017-03