Comparing Mixed-Integer and Constraint Programming for the No-Wait Flow Shop Problem with Due Date Constraints

Authors

  • Hamed Samarghandi Department of Finance and Management Science, Edwards School of Business, University of Saskatchewan, Saskatoon, Saskatchewan, Canada, S7N 5A7
Abstract:

The impetus for this research was examining a flow shop problem in which tasks were expected to be successively carried out with no time interval (i.e., no wait time) between them. For this reason, they should be completed by specific dates or deadlines. In this regard, the efficiency of the models was evaluated based on makespan. To solve the NP-Hard problem, we developed two mathematical models. Once we solved our problem using Mixed-Integer Programming Model (henceforth MIPM) and then, we applied a Constraint Programming Model (CPM); finally, we compared the optimality of the presented results.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

Solving Re-entrant No-wait Flow Shop Scheduling Problem

In this study, we consider the production environment of no-wait reentrant flow shop with the objective of minimizing makespan of the jobs. In a reentrant flow shop, at least one job should visit at least one of the machines more than once. In a no-wait flowshop scheduling problem, when the process of a specific job begins on the first machine, it should constantly be processed without waiting ...

full text

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

full text

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

full text

MILP Formulation and Genetic Algorithm for Non-permutation Flow Shop Scheduling Problem with Availability Constraints

In this paper, we consider a flow shop scheduling problem with availability constraints (FSSPAC) for the objective of minimizing the makespan. In such a problem, machines are not continuously available for processing jobs due to preventive maintenance activities. We proposed a mixed-integer linear programming (MILP) model for this problem which can generate non-permutation schedules. Furthermor...

full text

Mixed Integer Linear Programs for Blocking and No Wait Job Shop Scheduling Problems in Robotic cells

This paper studies the problem of scheduling Job shops in robotic cells with no intermediate buffers, called No Wait Blocking Transport Job Shop Scheduling Problem (NWBT JSSP). This problem is an extension of the classical job shop problem. No Wait Blocking Transport job shop problems arise in many realistic production environments. To tackle this problem, we developed a Mixed Integer Linear Pr...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 4  issue 1

pages  17- 24

publication date 2019-06-01

By following a journal you will be notified via email when a new issue of this journal is published.

Hosted on Doprax cloud platform doprax.com

copyright © 2015-2023