A New Mathematical Approach based on Conic Quadratic Programming for the Stochastic Time-Cost Tradeoff Problem in Project Management
Authors
Abstract:
In this paper, we consider a stochastic Time-Cost Tradeoff Problem (TCTP) in PERT networks for project management, in which all activities are subjected to a linear cost function and assumed to be exponentially distributed. The aim of this problem is to maximize the project completion probability with a pre-known deadline to a predefined probability such that the required additional cost is minimized. A single path TCTP is constructed as an optimization problem with decision variables of activity mean durations. We then reformulate the single path TCTP as a cone quadratic program in order to apply polynomial time interior point methods to solve the reformulation. Finally, we develop an iterative algorithm based on Monte Carlo simulation technique and conic optimization to solve general TCTP. The proposed approach has been tested on some randomly generated test problems. The results illustrate the good performance of our new approach.
similar resources
a new mathematical approach based on conic quadratic programming for the stochastic time-cost tradeoff problem in project management
in this paper, we consider a stochastic time-cost tradeoff problem (tctp) in pert networks for project management, in which all activities are subjected to a linear cost function and assumed to be exponentially distributed. the aim of this problem is to maximize the project completion probability with a pre-known deadline to a predefined probability such that the required additional cost is min...
full textA New Approach for Solving Interval Quadratic Programming Problem
This paper discusses an Interval Quadratic Programming (IQP) problem, where the constraints coefficients and the right-hand sides are represented by interval data. First, the focus is on a common method for solving Interval Linear Programming problem. Then the idea is extended to the IQP problem. Based on this method each IQP problem is reduced to two classical Quadratic Programming (QP) proble...
full textThe stochastic time-cost tradeoff problem: A robust optimization approach
We consider the problem of allocating resources to projects performed under given due dates and stochastic time–cost tradeoff settings. In particular, we show how to implement a state-of-the-art methodology known as “robust optimization” to solve the problem. In contrast to conventional approaches, the model we develop results in management policies rather than optimal values for the original d...
full textEffects of Project Uncertainties on Nonlinear Time-Cost Tradeoff Profile
This study presents the effects of project uncertainties on nonlinear time-cost tradeoff (TCT) profile of real life engineering projects by the fusion of fuzzy logic and artificial neural network (ANN) models with hybrid meta-heuristic (HMH) technique, abridged as Fuzzy-ANN-HMH. Nonlinear time-cost relationship of project activities is dealt with ANN models. ANN models are then integrated with ...
full textA NEW APPROACH FOR SOLVING FULLY FUZZY QUADRATIC PROGRAMMING PROBLEMS
Quadratic programming (QP) is an optimization problem wherein one minimizes (or maximizes) a quadratic function of a finite number of decision variable subject to a finite number of linear inequality and/ or equality constraints. In this paper, a quadratic programming problem (FFQP) is considered in which all cost coefficients, constraints coefficients, and right hand side are characterized by ...
full textMy Resources
Journal title
volume 24 issue 3
pages 177- 187
publication date 2013-09