A Multi-objective optimization model for project scheduling with time-varying resource requirements and capacities

Authors

  • Farhad Habibi School of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran
  • Farnaz Barzinpour School of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran
  • Seyed Jafar Sadjadi School of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran
Abstract:

Proper and realistic scheduling is an important factor of success for every project. In reality, project scheduling often involves several objectives that must be realized simultaneously, and faces numerous uncertainties that may undermine the integrity of the devised schedule. Thus, the manner of dealing with such uncertainties is of particular importance for effective planning. A realistic schedule must also take account of the time-based variations in the capacity of renewable resources and the amount of resources needed to undertake the activities and the overall effect of such variations on the schedule. In this study, we propose a multi-objective project scheduling optimization model with time-varying resource requirements and capacities.This model, with the objectives of minimizing the project makespan, maximizing the schedule robustness, and maximizing the net present value, considers the interests of both project owner and contractor simultaneously. Two multi-objective solution algorithms, NSGA-II and MOPSO, are modified and adjusted with Taguchi method to be used for determination of the set of Pareto optimal solutions for the proposed problem. The proposed solution methods are evaluated by the use of fifteen problems of different sizes derived from Project Scheduling Problem Library (PSPLIB). Finally, solutions of the algorithms are evaluated in terms of five evaluation criteria. The comparisons show that NSGA-II yields better results than MOPSO algorithm. Also, we show that ignoring the time-based variations in consumption and availability of resources may lead to underestimation of project makespan and significant deviation from the optimal activity sequence.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project

This paper presents a multi-objective resource-constrained project scheduling problem with positive and negative cash flows. The net present value (NPV) maximization and making span minimization are this study objectives. And since this problem is considered as complex optimization in NP-Hard context, we present a mathematical model for the given problem and solve three evolutionary algorithms;...

full text

A multi-objective resource-constrained project scheduling problem with time lags and fuzzy activity durations

The resource-constrained project scheduling problem is to find a schedule that minimizes the project duration subject to precedence relations and resource constraints. To further account for economic aspects of the project, one may add an objective of cash nature to the problem. In addition, dynamic nature and variations in real world are known to introduce uncertainties into data. Therefore, t...

full text

Modeling and Solution Procedure for a Preemptive Multi-Objective Multi-Mode Project Scheduling Model in Resource Investment Problems

In this paper, a preemptive multi-objective multi-mode project scheduling model for resource investment problem is proposed. The first objective function is to minimize the completion time of project (makespan);the second objective function is to minimize the cost of using renewable resources. Non-renewable resources are also considered as parameters in this model. The preemption of activities ...

full text

a multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project

this paper presents a multi-objective resource-constrained project scheduling problem with positive and negative cash flows. the net present value (npv) maximization and making span minimization are this study objectives. and since this problem is considered as complex optimization in np-hard context, we present a mathematical model for the given problem and solve three evolutionary algorithms;...

full text

Optimization of an energy based bi-objective multi skilled resource investment project scheduling problem

Growing concern in the management of energy due to the increasing energy costs, has forced managers to optimize the amount of energy required to provide products and services. This research integrates an energy-based resource investment project-scheduling problem (RIP) under a multi-skilled structure of the resources. The proposed energy based multi skilled resource investment problem (EB-MSRIP...

full text

A Multi-objective Scheduling Model for Solving the Resource-constrained Project Scheduling and Resource Leveling Problems

The project resource leveling problem was proposed to smooth resource usage and reduce resource fluctuation, while the resource-constrained project scheduling problem focuses on minimizing the project duration with limited resources. Solving the two interrelated problems separately is unlikely to result in a globally optimum schedule. The few integrated optimization methods that have been devel...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 10  issue special issue on scheduling

pages  92- 118

publication date 2017-11-28