Multi diameter pigging for Åsgard Commissioning and pigging the 710 km 42 " x 28 " Åsgard Pipeline
نویسندگان
چکیده
Statoil has designed and tested dual diameter pipeline pigs to perform various tasks during operations, precommissioning and commissioning of the 710km 42"x28" Åsgard pipeline. The concepts developed have been put through a major design and testing program to demonstrate that the various functional requirements have been met. The paper describes the development process as well as field experience from the initial pigging runs of the Åsgard Pipeline. Background The Åsgard field, currently the world’s largest subsea development, comprises of a large number of subsea manifolds connected to two processing facilities. the Asgard A FPSO oil centre and the Åsgard B semisubmersible gas centre. The Åsgard Transport Pipeline will transport dense phase hydrocarbon gas approx. 710km from Åsgard B to the onshore processing terminal at Kårstø. The diameter of the pipeline is 42”, but the water depth excluded a conventional 42” steel riser. Production will therefore be achieved using a number of 16" flexible risers connected to a subsea Export Riser Base (ERB). The Åsgard Project and partners initially evaluated a conventional 42” subsea launching facility against a reduced diameter concept. The 42” launcher enabling the use of conventional single diameter pigs, but at a high cost and high-risk development for the subsea structure. The alternative of a 28” sub sea launcher was eventually selected, which required specially designed 28”/42” pigs. The 28" ERB is connected to the 42" pipeline via a 28" expansion spool with mechanical connectors and a 28” to 42” transition piece. Operational pigs will be pre-loaded into cassettes, lowered to the seabed and connected to the 28” manifold prior to launching through the 28” section of line and into the 42” pipeline for travel the 710 km to the onshore plant at Kårstø. During precommissioning and commissioning of the pipeline, pigs have been run the opposite direction, from the landfall site, in order to perform flooding, cleaning, electronic gauging and de-watering of the line. These activities are referred to as the RFO tasks (Ready For Operation).
منابع مشابه
Stress Analysis of Oil Pipe Bend in a Hilly Region Under Pigging Conditions
Pigging is a significant part of a pipeline system that is required for production and operational maintenance. However, if the bend is not set properly, it is likely to cause congestion, which could cause the pipeline system to deviate from its normal operation or even lead to cracks or explosions due to overloaded stress. Due to the potential risk mentioned above, this report aims to build an...
متن کاملInspection of Buried or Inaccessable Piping in Nuclear Power Plants Utilizing Ultrasonic Based Intelligent Pigging Technology
Buried or inaccessible piping systems within Nuclear Power plants present a challenge in terms of overall inspection. Limited access and complex piping configurations restrict the type of indirect or direct NDE methodologies which can be applied by inspectors. Due to the complexity of buried and above-grade piping systems routed in and around these facilities, many plants have been forced to lo...
متن کاملA Novel Method to Enhance Pipeline Trajectory Determination Using Pipeline Junctions
Pipeline inspection gauges (pigs) have been used for many years to perform various maintenance operations in oil and gas pipelines. Different pipeline parameters can be inspected during the pig journey. Although pigs use many sensors to detect the required pipeline parameters, matching these data with the corresponding pipeline location is considered a very important parameter. High-end, tactic...
متن کاملCopyright © 2013 Pigging Products & Services Association DIFFICULT TO PIG AND TO INSPECT OFFSHORE PIPES
Introduction When it comes to a fast, non-intrusive, complete and meaningful inspection of an offshore pipeline in-line inspection (ILI) has been the method of choice for several decades now. However, not all pipelines, piping or other tubular structures can be inspected with in-line inspection tools (pigs). The method is usually limited to looping flow lines or export pipelines, specifically d...
متن کامل