Linac Commissioning for the Heavy Ion Cancer Therapy Facility HIT

نویسندگان

  • M. Maier
  • B. Schlitt
  • C. Kleffner
  • W. Barth
چکیده

The accelerator part of the clinical facility for cancer therapy HIT using energetic proton and ion beams (C, He and O) has been installed during 2006 at the Radiologische Universitätsklinik in Heidelberg, Germany [1]. The commissioning of the injector linac was performed in three steps for the LEBT, the RFQ and the IH-DTL and has successfully ended in December 2006. Some major results are briefly reported in this contribution. Introduction The commissioning of the linac shown schematically in Figure 1 was done in three consecutive steps as listed in Table 1 starting in April 2006 [2][3]. For each commissioning step a dedicated beam diagnostics test bench was designed to allow for beam current-, profile-, energyand emittance measurements. Different ion species were used: H2, H3, He, He, C and O. In this contribution selected results for C are reported. Profile grid L2DG1 Profile grids N1DG1/2 Profile grid I1DG3 Figure 1: Overview of the injector linac (solenoids SOL, quadrupole triplets QT, doublets QD, singlets QS). Table 1: Assembly and commissioning milestones. LEBT Figure 2 shows a typical ion source spectrum obtained for carbon operation. The specified intensity of the separated C beam from the ion source is 200 eμA. The beam profiles along the LEBT are shown in Figure 3 (for the grid positions compare to Figure 1). For this setting a beam current of 184 eμA corresponding to a transmission of 92 % in the LEBT was achieved. Figure 2: Ion source spectrum for carbon operation. Figure 3: Beam profiles along the LEBT for C. RFQ Before installation of the RFQ in Heidelberg, the RFQ had been investigated and tested with proton beams at a dedicated test bench at GSI [4]. As an example of measurements performed in Heidelberg, Figure 4 shows the energy of the C beam behind of the RFQ versus the tank voltage. The working point of the RFQ is marked, as well as the energy range required for injection into the adjacent IH-DTL. Figure 4: Beam energy measurements versus tank voltage to determine the RFQ working point for C. November 05 − March 06 LEBT, ECRIS installation & functional tests of components April / May 06 ECRIS May – July 06 LEBT successful beam commissioning July / August 06 RFQ installation of RFQ & testbench, RF commissioning September 06 RFQ beam acceleration to 400 keV/u October 06 IH-DTL completing of linac with IH-DTL & stripper-section November 06 IH-DTL RF commissioning December 06 IH-DTL first 7 MeV/u C beams (35 eμA) N1DG1 N1DG2 L2DG1 EXTERNAL-HIT-02

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Beam Diagnostics for the HIT and CNAO medical accelerators

A. Peters, M. Schwickert, A. Reiter and C. Dorn, GSI, Darmstadt, Germany Introduction In June 2003 it was decided that the GSI Beam Diagnostics (BD) group would act as contractor for the delivery of beam diagnostic devices for the heavy-ion cancer therapy facility HIT in Heidelberg. The contract included the production of the mechanical parts (feed-throughs, detectors etc.) as well as the integ...

متن کامل

Status of the Linac for the Italian Hadron-Therapy Centre CNAO

The Italian hadron-therapy centre CNAO (Centro Nazionale di Adroterapia Oncologica) [1] is designed for the treatment of tumours with proton and light ion beams and to clinical and radiobiological research. The design consists of two ECR ion sources, a 7 MeV/u injector linac identical to the linac of the Heidelberg ion therapy centre HIT [2][3] and a 400 MeV/u synchrotron. GSI delivers technica...

متن کامل

The comparison between 6 MV Primus LINAC simulation output using EGSnrc and commissioning data

Introduction: Monte Carlo calculation method is considered to be the most accurate method for dose calculation in radiotherapy. The purpose of this research is comparison between 6 MV Primus LINAC simulation output with commissioning data using EGSnrc and build a Monte Carlo geometry of 6 MV Primus LINAC as realistically as possible. The BEAMnrc and DOSXYZnrc (EGSnrc package) M...

متن کامل

COMMISSIONING OF THE 1.4 MeV/u HIGH CURRENT HEAVY ION LINAC AT GSI

The disassembly of the Unilac prestripper linac of the Wideröe type took place at the beginning of 1999. An increase of more than two orders of magnitude in particle number for the most heavy elements in the SIS had to be gained. Since that time the new High Current Injector (HSI) consisting of H-type RFQ and DTLstructures for dual beam operation was installed and successfully commissioned. The...

متن کامل

Operating Experience of the J-PARC Linac

The beam commissioning of the J-PARC linac started in November 2006 and 181 MeV acceleration was successfully achieved in January 2007. The linac has delivered beams to the 3 GeV Rapid Cycling Synchrotron for its commissioning, and then, the subsequent Main Ring Synchrotron and the neutron target commissioning. The linac uses a Cs-free LaB6-driven ion source and 20 units of 324 MHz klystrons. A...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2007