Abstract We consider a variant of the NP-hard problem assigning jobs to machines minimize completion time last job. Usually, precedence constraints are given by partial order on set jobs, and each job requires all its predecessors be completed before it can start. In this paper, we different type relation that has not been discussed as extensively is called OR-precedence. for start, require at ...