Abstract Engineering projects are notoriously hard to complete on-time, with project delays often theorised propagate across interdependent activities. Here, we use a novel dataset consisting of activity networks from 14 diverse, large-scale engineering uncover network properties that impact timely completion. We provide empirical evidence perturbation cascades, where perturbations in the deliv...