Journal: :Kybernetika 2011
Jan Pelikán

The subject of this paper is a flow-shop based on a case study aimed at the optimisation of ordering production jobs in mechanical engineering, in order to minimize the overall processing time, the makespan. The production jobs are processed by machines, and each job is assigned to a certain machine for technological reasons. Before processing a job, the machine has to be adjusted; there is onl...

  In this paper, we consider a flow shop scheduling problem with bypass consideration for minimizing the sum of earliness and tardiness costs. We propose a new mathematical modeling to formulate this problem. There are several constraints which are involved in our modeling such as the due date of jobs, the job ready times, the earliness and the tardiness cost of jobs, and so on. We apply adapte...

2013
Jaroslaw Pempera Czeslaw Smutnicki Dominik Zelazny

We consider the flow shop scheduling problem with minimizing two criteria simultaneously: the total completion time (makespan) and the sum of tardiness of jobs. The problem is strongly NP-hard, since for each separate criteria the problem is strongly NP-hard. There is a number of heuristic algorithms to solve the flow shop problem with various single objectives, but usage of those heuristics to...

2013
Mohammad Mirabi

Flow-shop scheduling problem (FSP) deals with the scheduling of a set of jobs that visit a set of machines in the same order. The FSP is NP-hard, which means that an efficient algorithm for solving the problem to optimality is unavailable. To meet the requirements on time and to minimize the make-span performance of large permutation flow-shop scheduling problems in which there are sequence dep...

Journal: :J. Scheduling 2011
Peter Brucker Natalia V. Shakhlevich

We study an inverse counterpart of the two machine flow-shop scheduling problem that arises in the context of inverse optimization. While in the forward scheduling problem all parameters are given and the objective is to find job sequence(s) for which the value of the makespan is minimum, in the inverse scheduling the exact values of processing times are unknown and they should be selected with...

2006
Tzung-Pei Hong Pei-Ying Huang Gwoboa Horng

In simple flow shop problems, each machine operation center includes just one machine. If at least one machine center includes more than one machine, the scheduling problem becomes a flexible flow-shop problem. Recently, group scheduling has also been proposed and discussed. In the group scheduling, each job belongs to a specific group and all the jobs are processed group by group. In this pape...

2010
Ashwani Dhingra Pankaj Chandna

In this work, multicriteria decision making objective for flow shop scheduling with sequence dependent set up time and due dates have been developed. Multicriteria decision making objective includes total tardiness, total earliness and makespan simultaneously which is very effective decision making for scheduling jobs in modern manufacturing environment. As problem of flow shop scheduling is NP...

2015
Liu Dongdong Liu Kai Zhao Zhengping Han

Traditional flexible flow shop scheduling cannot adapt to the work processes with existence of parallel machines, and blocks or limits the processes with no-wait constraints. Firstly, according to the problem in NWBFFSSP, which minimizes the maximum time used in the flow shop, an optimal solving model has been designed to realize the flexible flow shop scheduling with multi constraints; besides...

Journal: :international journal of industrial mathematics 2015
s. molla-alizadeh-‎zavardehi‎ r. tavakkoli-‎moghaddam f. hosseinzadeh ‎lotfi‎

‎in this paper, we study a flow shop batch processing machines scheduling problem. the fuzzy due dates are considered to make the problem more close to the reality. the objective function is taken as the weighted sum of fuzzy earliness and fuzzy tardiness. in order to tackle the given problem, we propose a hybrid electromagnetism-like (em) algorithm, in which the em is hybridized with a diversi...

Journal: :journal of optimization in industrial engineering 2013
javad rezaeian hany seidgar morteza kiani

this paper presents a new mathematical model for a hybrid flow shop scheduling problem with multiprocessor tasks in which sequence dependent set up times and preemption are considered. the objective is to minimize the weighted sum of makespan and maximum tardiness. three meta-heuristic methods based on genetic algorithm (ga), imperialist competitive algorithm (ica) and a hybrid approach of ga a...