[ 1 ] - Multi-Objective Unrelated Parallel Machines Scheduling with Sequence-Dependent Setup Times and Precedence Constraints
This paper presents a novel, multi-objective model of a parallel machines scheduling problem that minimizes the number of tardy jobs and total completion time of all jobs. In this model, machines are considered as unrelated parallel units with different speeds. In addition, there is some precedence, relating the jobs with non-identical due dates and their ready times. Sequence-dependent setup t...