نوروزی, محمدعلی
دانشگاه آزاد تهران جنوب
[ 1 ] - بهبود جبرانسازی راهاندازی توربین انبساطی توسط DVR بهبودیافته و STATCOM در نیروگاه نکا تحت شرایط خطا
In order to prevent energy waste by throttle valve in gas pressure reducing station of Neka thermal power plant, a turbo-expander with a capacity of 9.8 MW for the power plant was prepared and installed. Due to the absorption of 63 MVAr reactive powers at the moment of turbo-expander starting, resulted in severe voltage drops in the power plant auxiliary service system. In this paper, while pat...
نویسندگان همکار