Minimizing the total tardiness and makespan in an open shop scheduling problem with sequence-dependent setup times

نویسندگان

  • Reza Tavakkoli-Moghaddam Department of Industrial Engineering, College of Engineering, University of Tehran, PC: 14399-57131, Tehran, Iran
  • Samaneh Noori-Darvish Department of Industrial Engineering, Allame Mohades Noori University, PC: 46415-451, Noor, Iran
چکیده مقاله:

We consider an open shop scheduling problem with setup and processing times separately such that not only the setup times are dependent on the machines, but also they are dependent on the sequence of jobs that should be processed on a machine. A novel bi-objective mathematical programming is designed in order to minimize the total tardiness and the makespan. Among several multi-objective decision making (MODM) methods, an interactive one, called the TH method is applied for solving small-sized instances optimally and obtaining Pareto-optimal solutions by the Lingo software. To achieve Pareto-optimal sets for medium to large-sized problems, an improved non-dominated sorting genetic algorithm II (NSGA-II) is presented that consists of a heuristic method for obtaining a good initial population. In addition, by using the design of experiments (DOE), the efficiency of the proposed improved NSGA-II is compared with the efficiency of a well-known multi-objective genetic algorithm, namely SPEAII. Finally, the performance of the improved NSGA-II is examined in a comparison with the performance of the traditional NSGA-II.

برای دانلود باید عضویت طلایی داشته باشید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Minimizing the maximum tardiness and makespan criteria in a job shop scheduling problem with sequence dependent setup times

The job shop scheduling problem (JSP) is one of the most difficult problems in traditional scheduling because any job consists of a set operations and also any operation processes by a machine. Whereas the operation is placed in the machine, it is essential to be considering setup times that the times strongly depend on the various sequencing of jobs on the machines. This research is developed ...

متن کامل

A comparison of algorithms for minimizing the sum of earliness and tardiness in hybrid flow-shop scheduling problem with unrelated parallel machines and sequence-dependent setup times

In this paper, the flow-shop scheduling problem with unrelated parallel machines at each stage as well as sequence-dependent setup times under minimization of the sum of earliness and tardiness are studied. The processing times, setup times and due-dates are known in advance. To solve the problem, we introduce a hybrid memetic algorithm as well as a particle swarm optimization algorithm combine...

متن کامل

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

متن کامل

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

متن کامل

Makespan Minimization in the Flow-shop Scheduling Problem with Sequence Dependent Setup Times

In this paper, we address the problem of finding a permutation schedule of n jobs in an m machine flow-shop environment that minimizes the maximum completion time Cmax (Makespan) of all jobs. The jobs are available at time zero and have sequence-dependent setup times on each machine. All parameters, such as processing and setup times, are assumed to be known with certainty. This problem is clas...

متن کامل

an assembly flow-shop scheduling problem with sequence-dependent setup and transportation times

in this paper, three-stage assembly flowshop scheduling is considered with respect to minimizing bi-objectives, namely mean flow time and mean tardiness. this problem is a model of production systems, which several production operations are done simultaneously and independently, and then produced components are collected and transferred to an assembly stage for the final operation. in this mode...

متن کامل

منابع من

با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

ذخیره در منابع من قبلا به منابع من ذحیره شده

{@ msg_add @}


عنوان ژورنال

دوره 8  شماره 1

صفحات  -

تاریخ انتشار 2012-01-01