Three Hybrid Metaheuristic Algorithms for Stochastic Flexible Flow Shop Scheduling Problem with Preventive Maintenance and Budget Constraint

Authors

  • Ramtin Rooeinfar School of Industrial Engineering, South Tehran Branch, Islamic Azad University, Tehran, Iran
  • Sadigh Raissi School of Industrial Engineering, South Tehran Branch, Islamic Azad University, Tehran, Iran
  • Vahid Reza Ghezavati School of Industrial Engineering, South Tehran Branch, Islamic Azad University, Tehran, Iran
Abstract:

Stochastic flexible flow shop scheduling problem (SFFSSP) is one the main focus of researchers due to the complexity arises from inherent uncertainties and also the difficulty of solving such NP-hard problems. Conventionally, in such problems each machine’s job process time may encounter uncertainty due to their relevant random behaviour. In order to examine such problems more realistically, fixed interval preventive maintenance (PM) and budget constraint are considered.PM activity is a crucial task to reduce the production efficiency. In the current research we focused on a scheduling problem which a job is processed at the upstream stage and all the downstream machines get busy or alternatively PM cost is significant, consequently the job waits inside the buffers and increases the associated holding cost. This paper proposes a new more realistic mathematical model which considers both the PM and holding cost of jobs inside the buffers in the stochastic flexible flow shop scheduling problem. The holding cost is controlled in the model via the budget constraint. In order to solve the proposedmodel, three hybrid metaheuristic algorithms are introduced. They include a couple of well-known metaheuristic algorithms which have efficient quality solutions in the literature. The two algorithms of them constructed byincorporationof the particle swarm optimization algorithm (PSO) and parallel simulated annealing (PSA) methods under different random generation policies. The third one enriched based on genetic algorithm (GA) with PSA. To evaluate the performance of the proposed algorithms, different numerical examples are presented. Computational experiments revealed that the proposed algorithms embedboth desirable accuracy and CPU time. Among them, the PSO-PSAП outperforms than other algorithms in terms of makespan and CPU time especially for large size problems.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

Three Algorithms for Flexible Flow-shop Scheduling

Scheduling is an important process widely used in manufacturing, production, management, computer science, and so on. Appropriate scheduling can reduce material handling costs and time. Finding good schedules for given sets of jobs can thus help factory supervisors effectively control job flows and provide solutions for job sequencing. In simple flow shop problems, each machine operation center...

full text

Hybrid metaheuristic algorithms for the tardiness blocking flow shop problem

This paper proposes an Iterated Local Search (ILS) procedure and an Iterated Greedy (IG) algorithm, which are both combined with a variable neighbourhood search (VNS), for dealing with the flow shop problem with blocking, in order to minimize the total tardiness of jobs. The structure of both algorithms is very similar, but they differ in the way that the search is diversified in the space of s...

full text

Metaheuristic Algorithms for Hybrid Flow-Shop Scheduling Problem with Multiprocessor Tasks

This paper is concerned with hybrid flow-shop scheduling problem involving multiprocessor tasks. The hybrid flow-shop problem is a generalization of the classical flow-shop problem by permitting multiple parallel processors at each stage of task processing. The multiprocessor tasks, on the other hand, overcome the restriction of the classical scheduling problems by allowing tasks to be processe...

full text

Flow shop Scheduling Problem with Maintenance Coordination: a New Approach

This study investigates the coordination of production scheduling and maintenance planning in theflow shop scheduling environment. The problem is considered in a bi-objective form, minimizing themakespan as the production scheduling criterion and minimizing the system unavailability as themaintenance planning criterion. The time interval between consecutive maintenance activities as well as the...

full text

Modeling the Hybrid Flow Shop Scheduling Problem Followed by an Assembly Stage Considering Aging Effects and Preventive Maintenance Activities

Scheduling problem for the hybrid flow shop scheduling problem (HFSP) followed by an assembly stage considering aging effects additional preventive and maintenance activities is studied in this paper. In this production system, a number of products of different kinds are produced. Each product is assembled with a set of several parts. The first stage is a hybrid flow shop to produce parts. All ...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 12  issue 2

pages  131- 147

publication date 2019-07-01