Presenting a Multi-Objective Mathematical Model for Time-Cost trade off Problem Considering Time Value of Money and Solve it by MOPSO Algorithm

Authors

  • F hosseinzadeh lotfi Department of Mathematics, Science and Research Branch, Islamic Azad University, Tehran, Iran.
  • M.A Shafiiee PhD student of technology management, UAE Branch, Islamic Azad University, Dubai, UAE.
  • M.R Shahriyary Department of industrial management, South Tehran Branch, Islamic Azad University, Tehran, Iran.
Abstract:

The time - cost tradeoff problem is one of the most critical issues in the project scheduling field and so far, a lot of research has been done with a variety of quantitative and qualitative approaches on this subject. In this research, we intend to provide a two - objective mathematical model which balances crash and delay for activities. So that it provides the right tools for decision makers to decide on the scheduling of activities, with considering available facilities and time available, to complete the project. In the proposed mathematical model, it is attempting to use the assumptions such as the nonlinear cost function as well as the time value of money so that the problem conditions will be as close as possible to the real environment. At the end, we solve the mathematical model presented in this paper using the Multi Objective Particle Swarm Optimization (MOPSO) algorithm and the impact of the crash and delay for activities in the final non-dominated solutions is investigated.  

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

A New Heuristic Algorithm for Time-cost Trade-off Problem Taking into Account Monetary Value

Time-cost trade-off is one of the most important subjects in project management and of interest to contractors. The goal of time-cost trade-off is sensivity analysis of project costs to changes in activity duration in order to obtain the best combination of activity duration decrease, in a way that the sum of project costs is minimized. In the heuristics presented in this area, time crashing is...

full text

A New Heuristic Algorithm for Time-cost Trade-off Problem Taking into Account Monetary Value

Time-cost trade-off is one of the most important subjects in project management and of interest to contractors. The goal of time-cost trade-off is sensivity analysis of project costs to changes in activity duration in order to obtain the best combination of activity duration decrease, in a way that the sum of project costs is minimized. In the heuristics presented in this area, time crashing is...

full text

A New Mathematical Model for Time Cost Trade-off Problem with Budget Limitation Based on Time Value of Money

The main objective in the time cost trade-off problems has always been the reduction in the total cost. In the previous researches the total cost function has been defined 3 * corresponding author e-Mail: [email protected]

full text

A mathematical model for balancing (cost-time-quality and environmental risks) in oil and gas projects and solving it by multi-objective Bee Colony Algorithm

Today, in large projects such as constructing oil, gas and petrochemical refineries, it is inevitable to use modern management methods and project timing. On the other hand, in classic scheduling case, the focus is on balance between time and cost of carrying out projects, which in such a situation, one of possible solutions to shorten time of implementing project is to accelerate activities. T...

full text

A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project

This paper presents a multi-objective resource-constrained project scheduling problem with positive and negative cash flows. The net present value (NPV) maximization and making span minimization are this study objectives. And since this problem is considered as complex optimization in NP-Hard context, we present a mathematical model for the given problem and solve three evolutionary algorithms;...

full text

MULTI-OBJECTIVE OPTIMIZATION OF TIME-COST-SAFETY USING GENETIC ALGORITHM

Safety risk management has a considerable effect on disproportionate injury rate of construction industry, project cost and both labor and public morale. On the other hand time-cost optimization (TCO) may earn a big profit for project stakeholders. This paper has addressed these issues to present a multi-objective optimization model to simultaneously optimize total time, total cost and overall ...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 4  issue شماره 2 (پیاپی 14)

pages  35- 50

publication date 2018-07-23