Modeling the Hybrid Flow Shop Scheduling Problem Followed by an Assembly Stage Considering Aging Effects and Preventive Maintenance Activities
author
Abstract:
Scheduling problem for the hybrid flow shop scheduling problem (HFSP) followed by an assembly stage considering aging effects additional preventive and maintenance activities is studied in this paper. In this production system, a number of products of different kinds are produced. Each product is assembled with a set of several parts. The first stage is a hybrid flow shop to produce parts. All machines can process all kinds of parts in this stage but each machine can process only one part at the same time. The second stage is a single assembly machine or a single assembly team of workers. The aim is to schedule the parts on the machines and assembly sequence and also determine when the preventive maintenance activities get done in order to minimize the completion time of all products (makespan). A mathematical modeling is presented and its validation is shown by solving an example in small scale. Since this problem has been proved strongly NP-hard, in order to solve the problem in medium and large scale, four heuristic algorithms is proposed based on the Johnson’s algorithm. The numerical experiments are used to run the mathematical model and evaluate the performance of the proposed algorithms.
similar resources
Modelling and solving the job shop scheduling Problem followed by an assembly stage considering maintenance operations and access restrictions to machines
This paper considers job shop scheduling problem followed by an assembly stage and Lot Streaming (LS). It is supposed here that a number of products have been ordered to be produced. Each product is assembled with a set of several parts. The production system includes two stages. The first stage is a job shop to produce parts. Each machine can process only one part at the same time. The second ...
full textThree Hybrid Metaheuristic Algorithms for Stochastic Flexible Flow Shop Scheduling Problem with Preventive Maintenance and Budget Constraint
Stochastic flexible flow shop scheduling problem (SFFSSP) is one the main focus of researchers due to the complexity arises from inherent uncertainties and also the difficulty of solving such NP-hard problems. Conventionally, in such problems each machine’s job process time may encounter uncertainty due to their relevant random behaviour. In order to examine such problems more realistically, fi...
full textHybrid algorithms for Job shop Scheduling Problem with Lot streaming and A Parallel Assembly Stage
In this paper, a Job shop scheduling problem with a parallel assembly stage and Lot Streaming (LS) is considered for the first time in both machining and assembly stages. Lot Streaming technique is a process of splitting jobs into smaller sub-jobs such that successive operations can be overlapped. Hence, to solve job shop scheduling problem with a parallel assembly stage and lot streaming, deci...
full textA three-stage assembly flow shop scheduling problem with blocking and sequence-dependent set up times
This paper considers a three-stage assembly flowshop scheduling problem with sequence-dependent setup < /div> times at the first stage and blocking times between each stage in such a way that the weighted mean completion time and makespan are minimized. Obtaining an optimal solution for this type of complex, large-sized problem in reasonable computational time using traditiona...
full textA multi-objective genetic algorithm (MOGA) for hybrid flow shop scheduling problem with assembly operation
Scheduling for a two-stage production system is one of the most common problems in production management. In this production system, a number of products are produced and each product is assembled from a set of parts. The parts are produced in the first stage that is a fabrication stage and then they are assembled in the second stage that usually is an assembly stage. In this article, the first...
full textModeling and scheduling no-idle hybrid flow shop problems
Although several papers have studied no-idle scheduling problems, they all focus on flow shops, assuming one processor at each working stage. But, companies commonly extend to hybrid flow shops by duplicating machines in parallel in stages. This paper considers the problem of scheduling no-idle hybrid flow shops. A mixed integer linear programming model is first developed to mathematically form...
full textMy Resources
Journal title
volume 3 issue 1
pages 1215- 1233
publication date 2016-05