Minimizing the maximum tardiness and makespan criteria in a job shop scheduling problem with sequence dependent setup times

Authors

  • Adel Aazami School of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran
  • Mehdi Heydari School of Industrial Engineering, Iran University of Science and Technology, Tehran, Iran
Abstract:

The job shop scheduling problem (JSP) is one of the most difficult problems in traditional scheduling because any job consists of a set operations and also any operation processes by a machine. Whereas the operation is placed in the machine, it is essential to be considering setup times that the times strongly depend on the various sequencing of jobs on the machines. This research is developed a two-objective model to solve JSP with sequence-dependent setup times (SDST). Considering SDST and optimizing of the both objectives simultaneously (makespan and maximum tardiness) bring us closer to natural-world problems. The ε-constraint method is applied to solve the mentioned two-objective model. A set of numerical data is generated and tested to validate the model’s efficiency and flexibility. The developed model can efficiently use for solving JSPs in the real world, especially for manufacturing companies with having setup and delivery time’s constraints.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

Minimizing the total tardiness and makespan in an open shop scheduling problem with sequence-dependent setup times

We consider an open shop scheduling problem with setup and processing times separately such that not only the setup times are dependent on the machines, but also they are dependent on the sequence of jobs that should be processed on a machine. A novel bi-objective mathematical programming is designed in order to minimize the total tardiness and the makespan. Among several mult...

full text

A comparison of algorithms for minimizing the sum of earliness and tardiness in hybrid flow-shop scheduling problem with unrelated parallel machines and sequence-dependent setup times

In this paper, the flow-shop scheduling problem with unrelated parallel machines at each stage as well as sequence-dependent setup times under minimization of the sum of earliness and tardiness are studied. The processing times, setup times and due-dates are known in advance. To solve the problem, we introduce a hybrid memetic algorithm as well as a particle swarm optimization algorithm combine...

full text

A Job Shop Scheduling Problem with Sequence-Dependent Setup Times Considering Position-Based Learning Effects and Availability Constraints

 Sequence dependent set-up times scheduling problems (SDSTs), availability constraint and transportation times are interesting and important issues in production management, which are often addressed separately. In this paper, the SDSTs job shop scheduling problem with position-based learning effects, job-dependent transportation times and multiple preventive maintenance activities is studied. ...

full text

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

full text

Solving Group Scheduling Problem in No-wait Flow Shop with Sequence Dependent Setup Times

Different manufacturing enterprises use regularly scheduling algorithms in order to help meeting demands over time and reducing operational costs. Nowadays, for a better useofresources and manufacturingin accordance withcustomer needs and given the level ofcompetitionbetweencompanies, employing asuitablescheduling programhasa double importance. Conventional productionmethods are constantly subs...

full text

Makespan Minimization in the Flow-shop Scheduling Problem with Sequence Dependent Setup Times

In this paper, we address the problem of finding a permutation schedule of n jobs in an m machine flow-shop environment that minimizes the maximum completion time Cmax (Makespan) of all jobs. The jobs are available at time zero and have sequence-dependent setup times on each machine. All parameters, such as processing and setup times, are assumed to be known with certainty. This problem is clas...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 11  issue 2

pages  0- 0

publication date 2018-04-01

By following a journal you will be notified via email when a new issue of this journal is published.

Hosted on Doprax cloud platform doprax.com

copyright © 2015-2023