Estimation of Project Performance Using Earned Value Management and Fuzzy Regression

Authors

  • Ali Reza Mirzaei Department of Technology Management, Allameh Tabataba’ee University Tehran, Iran
  • Mohammad Mahdi Asgari Dehabadi Department of Industrial engineering, University of Economic Science Tehran, Iran
  • Mostafa Salari Department of Industrial engineering, Sharif University of Technology Tehran, Iran
Abstract:

Earned Value Management is a critical project managementmethodology that evaluates project performance from cost andschedule viewpoints. The novel theoretical framework presented in thispaper estimates future performance of project regarding the past relativeinformation. It benefits from fuzzy regression (FR) models in estimationprocess in order to deal with the vagueness and impreciseness ofreal data. Furthermore, fuzzy-based estimation is evaluated using linguisticterms to interpret different possible condition of projects. Theproposed model can greatly assists project managers to assess prospectiveperformance of project and alerts them in taking of necessaryactions. Finally, one illustrative case associated with a constructionproject has been provided to illustrate the applicability of theoreticalmodel in real situations.

similar resources

estimation of project performance using earned value management and fuzzy regression

earned value management is a critical project managementmethodology that evaluates project performance from cost andschedule viewpoints. the novel theoretical framework presented in thispaper estimates future performance of project regarding the past relativeinformation. it benefits from fuzzy regression (fr) models in estimationprocess in order to deal with the vagueness and impreciseness ofre...

full text

Predicting project time and costs using earned value management based on trapezoidal fuzzy numbers

Projects include activities that must be carried out at certain dates, with specified costs and determined qualities in order to satisfy the stakeholders. Project control is one of the most important and widely used issues in project-based organizations and it has attracted a lot of attention. So far, in the field of project control, there have been a lot of research that were done in different...

full text

A comparison of the performance of various project control methods using earned value management systems

Recent literature on project management has emphasised the effort which is spent by the management team during the project control process. Based on this effort, a functional distinction can be made between a top down and a bottom up project control approach. A top down control approach refers to the use of a project control system that generates project based performance metrics to give a gene...

full text

Self-Starting Control Chart and Post Signal Diagnostics for Monitoring Project Earned Value Management Indices

Earned value management (EVM) is a well-known approach in a project control system which uses some indices to track schedule and cost performance of a project. In this paper, a new statistical framework based on self-starting monitoring and change point estimation is proposed to monitor correlated EVM indices which are usually auto-correlated over time and non-normally distributed. Also, a new ...

full text

Using fuzzy FMEA and fuzzy logic in project risk management

Risk management is one of the most important phases of project management and isthe most recently used by many researchers. In this paper, a fuzzy based method wasproposed which identifies different kinds of risks through the project life cycle.Then, the project risk magnitude can be obtained in regards to five factors, namely“severity”, “occurrence”, and “not detection” which form fuzzy FMEA a...

full text

Earned - Value Management Terminology

To the Editor: Although I enjoyed the article titled “Value-Based Software Engineering: A Case Study” (Barry Boehm and Li Guo Huang, March 2003, pp. 33-41), as a newly minted Project Management Professional and a contributor to the Project Management Institute’s Earned Value Analysis team, I was disappointed with the authors’ use of nonstandard terminology. The authors renamed the traditional t...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 2  issue 1

pages  105- 122

publication date 2015-03-01

By following a journal you will be notified via email when a new issue of this journal is published.

Hosted on Doprax cloud platform doprax.com

copyright © 2015-2023