An Iterated Greedy Algorithm for Flexible Flow Lines with Sequence Dependent Setup Times to Minimize Total Weighted Completion Time

Authors

  • Bahman Naderi Department of Indusrial Engineering, Amirkabir University of Technology, Tehran, Iran
  • mostafa Zandieh Department of Industrial Management, Shahid Beheshti University,G.C., Tehran, Iran
  • Seyed Mohammad Taghi Fatemi Ghomi Department of Indusrial Engineering, Amirkabir University of Technology, Tehran, Iran
Abstract:

This paper explores the flexile flow lines where setup times are sequence- dependent. The optimization criterion is the minimization of total weighted completion time. We propose an iterated greedy algorithm (IGA) to tackle the problem. An experimental evaluation is conducted to evaluate the proposed algorithm and, then, the obtained results of IGA are compared against those of some other existing algorithms. The effectiveness of IGA is demonstrated through comparison.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

an iterated greedy algorithm for flexible flow lines with sequence dependent setup times to minimize total weighted completion time

this paper explores the flexile flow lines where setup times are sequence- dependent. the optimization criterion is the minimization of total weighted completion time. we propose an iterated greedy algorithm (iga) to tackle the problem. an experimental evaluation is conducted to evaluate the proposed algorithm and, then, the obtained results of iga are compared against those of some other exist...

full text

An Iterated Greedy Algorithm for Solving the Blocking Flow Shop Scheduling Problem with Total Flow Time Criteria

In this paper, we propose an iterated greedy algorithm for solving the blocking flow shop scheduling problem with total flow time minimization objective. The steps of this algorithm are designed very efficient. For generating an initial solution, we develop an efficient constructive heuristic by modifying the best known NEH algorithm. Effectiveness of the proposed iterated greedy algorithm is t...

full text

New scheduling rules for a dynamic flexible flow line problem with sequence-dependent setup times

In the literature, the application of multi-objective dynamic scheduling problem and simple priority rules are widely studied. Although these rules are not efficient enough due to simplicity and lack of general insight, composite dispatching rules have a very suitable performance because they result from experiments. In this paper, a dynamic flexible flow line problem with sequence-dependent se...

full text

An Iterated Greedy Algorithm for the Flowshop Problem with Sequence Dependent Setup Times

The flowshop problem (FSP) is one of the most thoroughly studied scheduling problems. In the FSP, a set N = {1, . . . , n} of n independent jobs has to be processed on a set M = {1, . . . ,m} of m machines. Every job j, j ∈ N , requires a given fixed, non-negative processing time pij on every machine i, i ∈ M . In a flowshop, all n jobs are to be processed on the m machines in the same order, t...

full text

An Effective Hybrid Genetic Algorithm for Hybrid Flow Shops with Sequence Dependent Setup Times and Processor Blocking

Hybrid flow-shop or flexible flow shop problems have remained subject of intensive research over several years. Hybrid flow-shop problems overcome one of the limitations of the classical flow-shop model by allowing parallel processors at each stage of task processing. In many papers the assumptions are generally made that there is unlimited storage available between stages and the setup times a...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume Volume 2  issue Issue 3

pages  33- 37

publication date 2010-02-07

By following a journal you will be notified via email when a new issue of this journal is published.

Hosted on Doprax cloud platform doprax.com

copyright © 2015-2023