An ex ante control chart for project monitoring using earned duration management observations

Authors

  • Morteza Bagherpour Department of Industrial Engineering, Iran University of Science and Technology, Narmak, Tehran, Iran
  • Rassoul Noorossana Department of Industrial Engineering, Iran University of Science and Technology, Narmak, Tehran, Iran
  • Seyed Taha Hossein Mortaji Department of Industrial Engineering, Iran University of Science and Technology, Narmak, Tehran, Iran
  • Siamak Noori Department of Industrial Engineering, Iran University of Science and Technology, Narmak, Tehran, Iran
Abstract:

In the past few years, there has been an increasing interest in developing project control systems. The primary purpose of such systems is to indicate whether the actual performance is consistent with the baseline and to produce a signal in the case of non-compliance. Recently, researchers have shown an increased interest in monitoring project’s performance indicators, by plotting them on the Shewhart-type control charts over time. However, these control charts are fundamentally designed for processes and ignore project-specific dynamics, which can lead to weak results and misleading interpretations. By paying close attention to the project baseline schedule and using statistical foundations, this paper proposes a new ex ante control chart which discriminates between acceptable (as-planned) and non-acceptable (not-as-planned) variations of the project’s schedule performance. Such control chart enables project managers to set more realistic thresholds leading to a better decision making for taking corrective and/or preventive actions. For the sake of clarity, an illustrative example has been presented to show how the ex ante control chart is constructed in practice. Furthermore, an experimental investigation has been set up to analyze the performance of the proposed control chart. As expected, the results confirm that, when a project starts to deflect significantly from the project’s baseline schedule, the ex ante control chart shows a respectable ability to detect and report right signals while avoiding false alarms.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

Self-Starting Control Chart and Post Signal Diagnostics for Monitoring Project Earned Value Management Indices

Earned value management (EVM) is a well-known approach in a project control system which uses some indices to track schedule and cost performance of a project. In this paper, a new statistical framework based on self-starting monitoring and change point estimation is proposed to monitor correlated EVM indices which are usually auto-correlated over time and non-normally distributed. Also, a new ...

full text

forecasting project duration by earned duration management and risk management

being observed frequently that projects cannot achieve to their plan duration and their budget. utilizing retrospective method is one of the reasons for this problem. in this research two method, earned duration management and risk management, has been used to remove the gap of the plan and the reality; this enable the project to utilize both high accuracy of the first method and prophecy of th...

full text

Setting tolerance limits for statistical project control using earned value management ¬リニ

Project control has been a research topic since decades that attracts both academics and practitioners. Project control systems indicate the direction of change in preliminary planning variables compared with actual performance. In case their current project performance deviates from the planned performance, a warning is indicated by the system in order to take corrective actions. Earned value ...

full text

Providing comprehensive control chart for monitoring of linear and nonlinear profiles using functional data analysis.

Considering profiles as functional variables, two control charts are proposed for their monitoring in phase II. Due to its conformity with the nature of real-world profiles, applying functional model leads to proposed control charts obtained through functional data analysis techniques with desired features. These include simplicity in calculation and possibility of using them for different prof...

full text

A multivariate approach for top-down project control using earned value management

a r t i c l e i n f o Project monitoring and the related decision to proceed to corrective action are crucial components of an integrated project management and control decision support system (DSS). Earned value management/earned schedule (EVM/ES) is a project control methodology that is typically applied for top-down project schedule control. However , traditional models do not correctly acco...

full text

A comparison of the performance of various project control methods using earned value management systems

Recent literature on project management has emphasised the effort which is spent by the management team during the project control process. Based on this effort, a functional distinction can be made between a top down and a bottom up project control approach. A top down control approach refers to the use of a project control system that generates project based performance metrics to give a gene...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 14  issue 4

pages  -

publication date 2018-12-01