A multi-objective resource-constrained project scheduling problem with time lags and fuzzy activity durations

Authors

  • alireza eydi Department of Industrial Engineering, University of Kurdistan, Sanandaj, Iran
  • mohsen bakhshi Department of Industrial Engineering, University of Kurdistan, Sanandaj, Iran
Abstract:

The resource-constrained project scheduling problem is to find a schedule that minimizes the project duration subject to precedence relations and resource constraints. To further account for economic aspects of the project, one may add an objective of cash nature to the problem. In addition, dynamic nature and variations in real world are known to introduce uncertainties into data. Therefore, this study is aimed at proposing a multi-objective model for resource-constrained project scheduling problem, with the model objectives being to minimize makespan, and maximize net present value of the project cash flows; the proposed model has activity times expressed in fuzzy numbers where the corresponding uncertainties are taken into account. The project environment is considered to be a multi-resource environment where more than one resource is needed for the execution of any activity. Also, the proposed model comes with time lags in precedence relations between activities. The proposed model is validated by using epsilon-constraint method. The α-cut approach as well as the expression of acceptable risk level by the project manager is used to defuzzificate fuzzy activity durations. Since the problem is NP-hard, a NSGA-II meta-heuristic algorithm is proposed to solve the problem. The algorithm performance has been evaluated in terms of different criteria.

Upgrade to premium to download articles

Sign up to access the full text

Already have an account?login

similar resources

A UNIFIED MODEL FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM WITH UNCERTAIN ACTIVITY DURATIONS

In this paper we present a unified (probabilistic/possibilistic) model for resource-constrained project scheduling problem (RCPSP) with uncertain activity durations and a concept of a heuristic approach connected to the theoretical model. It is shown that the uncertainty management can be built into any heuristic algorithm developed to solve RCPSP with deterministic activity durations. The esse...

full text

Modeling and solving multi-skilled resource-constrained project scheduling problem with calendars in fuzzy condition

In this study, we aim to present a new model for the resource-constrained project scheduling problem (RCPSP) considering a working calendar for project members and determined the skill factor of any member using the efficiency concept. For this purpose, the recyclable resources are staff resources where any person with multiple skills can meet the required skills of activities in a given time. ...

full text

The Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem

This paper presents the formulation and solution of the Combinatorial Multi-Mode Resource Constrained Multi-Project Scheduling Problem. The focus of the proposed method is not on finding a single optimal solution, instead on presenting multiple feasible solutions, with cost and duration information to the project manager. The motivation for developing such an approach is due in part to practica...

full text

A multi-objective resource-constrained optimization of time-cost trade-off problems in scheduling project

This paper presents a multi-objective resource-constrained project scheduling problem with positive and negative cash flows. The net present value (NPV) maximization and making span minimization are this study objectives. And since this problem is considered as complex optimization in NP-Hard context, we present a mathematical model for the given problem and solve three evolutionary algorithms;...

full text

A Bi-objective Pre-emption Multi-mode Resource Constrained Project Scheduling Problem with due Dates in the Activities

In this paper, a novel mathematical model for a preemption multi-mode multi-objective resource-constrained project scheduling problem with distinct due dates and positive and negative cash flows is presented. Although optimization of bi-objective problems with due dates is an essential feature of real projects, little effort has been made in studying the P-MMRCPSP while due dates are included i...

full text

A Multi-objective optimization model for project scheduling with time-varying resource requirements and capacities

Proper and realistic scheduling is an important factor of success for every project. In reality, project scheduling often involves several objectives that must be realized simultaneously, and faces numerous uncertainties that may undermine the integrity of the devised schedule. Thus, the manner of dealing with such uncertainties is of particular importance for effective planning. A realistic sc...

full text

My Resources

Save resource for easier access later

Save to my library Already added to my library

{@ msg_add @}


Journal title

volume 12  issue Special issue on Project Management and Control

pages  45- 71

publication date 2019-01-17

By following a journal you will be notified via email when a new issue of this journal is published.

Hosted on Doprax cloud platform doprax.com

copyright © 2015-2023