The total completion time open shop scheduling problem with a given sequence of jobs on one machine

نویسندگان

  • Ching-Fang Liaw
  • Chun-Yuan Cheng
  • Mingchih Chen
چکیده

This paper addresses the open shop scheduling problem to minimize the total completion time, provided that one of the machines has to process the jobs in a given sequence. The problem is NP-hard in the strong sense even for the two-machine case. A lower bound is derived based on the optimal solution of a relaxed problem in which the operations on every machine may overlap except for the machine with a given sequence of jobs. This relaxed problem is NP-hard in the ordinary sense, however it can be quickly solved via a decomposition into subset-sum problems. Both heuristic and branch-and-bound algorithm are proposed. Experimental results show that the heuristic is efficient for solving large-scaled problems, and the branch-and-bound algorithm performs well on small-scaled problems.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

A Hybrid Genetic Algorithm for the Open Shop Scheduling with Makespan and Total Completion Time

Proper scheduling of tasks leads to optimum using of time and resources, in order to obtaining best result. One of the most important and complicated scheduling problems is open shop scheduling problem. There are n jobs in open shop scheduling problem which should be processed by m machines. Purpose of scheduling open shop problem is attaining to a suitable order of processing jobs by specified...

متن کامل

A Hybrid Genetic Algorithm for the Open Shop Scheduling with Makespan and Total Completion Time

Proper scheduling of tasks leads to optimum using of time and resources, in order to obtaining best result. One of the most important and complicated scheduling problems is open shop scheduling problem. There are n jobs in open shop scheduling problem which should be processed by m machines. Purpose of scheduling open shop problem is attaining to a suitable order of processing jobs by specified...

متن کامل

Minimizing the total tardiness and makespan in an open shop scheduling problem with sequence-dependent setup times

We consider an open shop scheduling problem with setup and processing times separately such that not only the setup times are dependent on the machines, but also they are dependent on the sequence of jobs that should be processed on a machine. A novel bi-objective mathematical programming is designed in order to minimize the total tardiness and the makespan. Among several mult...

متن کامل

A Mathematical Analysis on Linkage of a Network of Queues with Two Machines in a Flow Shop including Transportation Time

This paper represents linkage network of queues consisting of biserial and parallel servers linked to a common server in series with a flowshop scheduling system consisting of two machines. The significant transportation time of the jobs from one machine to another is also considered. Further, the completion time of jobs/customers (waiting time + service time) in the queue network is the set...

متن کامل

Single Machine Scheduling Problem with Precedence Constraints and Deteriorating Jobs

This paper considers the single machine scheduling problem with precedence constraints and deteriorating jobs. A mathematical model based on binary integer programming (BIP) is developed. By these precedence constraints, jobs can not start before completion of its all predecessors. The represented model is in two steps, in step one the earliest starting time of each job is computed, then the re...

متن کامل

Two meta-heuristic algorithms for parallel machines scheduling problem with past-sequence-dependent setup times and effects of deterioration and learning

This paper considers identical parallel machines scheduling problem with past-sequence-dependent setup times, deteriorating jobs and learning effects, in which the actual processing time of a job on each machine is given as a function of the processing times of the jobs already processed and its scheduled position on the corresponding machine. In addition, the setup time of a job on each machin...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • Computers & OR

دوره 29  شماره 

صفحات  -

تاریخ انتشار 2002