Minimizing Makespan for a Flexible Flow Shop Scheduling Problem in a Paint Company
نویسندگان
چکیده
This paper focuses on a Flexible Flow Shop (FFS) problem in a paint company in an attempt to minimize production makespan. The FFS problem is characterized by multiple products being produced in machines in stages with sequence dependent set up times and infinite intermediate storages. As the FFS problem is computationally complex, two heuristic methods are employed to solve the Mixed Integer Linear Programming (MILP) problem formulated. The first heuristic is based on the Theory of Constraints and the second heuristic is based on a Genetic Algorithm. The Genetic Algorithm approach has resulted in a better production makespan.
منابع مشابه
A Mathematical Model for a Flow Shop Scheduling Problem with Fuzzy Processing Times
This paper presents a mathematical model for a flow shop scheduling problem consisting of m machine and n jobs with fuzzy processing times that can be estimated as independent stochastic or fuzzy numbers. In the traditional flow shop scheduling problem, the typical objective is to minimize the makespan). However,, two significant criteria for each schedule in stochastic models are: expectable m...
متن کاملA New Lower Bound for Flexible Flow Shop Problem with Unrelated Parallel Machines
Flexible flow shop scheduling problem (FFS) with unrelated parallel machines contains sequencing in flow shop where, at any stage, there exists one or more processors. The objective consists of minimizing the maximum completion time. Because of NP-completeness of FFS problem, it is necessary to use heuristics method to address problems of moderate to large scale problem. Therefore, for assessme...
متن کاملImproved teaching–learning-based and JAYA optimization algorithms for solving flexible flow shop scheduling problems
Flexible flow shop (or a hybrid flow shop) scheduling problem is an extension of classical flow shop scheduling problem. In a simple flow shop configuration, a job having ‘g’ operations is performed on ‘g’ operation centres (stages) with each stage having only one machine. If any stage contains more than one machine for providing alternate processing facility, then the problem...
متن کاملA novel mathematical model for a hybrid flow shop scheduling problem under buffer and resource limitations-A case study
Scheduling problems play a big role in manufacturing and planning the production for increasing the production efficiency and assigning the resources to operations. Furthermore, in many manufacturing systems there is a physical space between stages that called intermediate buffers. In this study, a model is proposed for minimizing the makespan of a hybrid flow shop scheduling problem with inter...
متن کاملOptimality of the flexible job shop scheduling system based on Gravitational Search Algorithm
The Flexible Job Shop Scheduling Problem (FJSP) is one of the most general and difficult of all traditional scheduling problems. The Flexible Job Shop Problem (FJSP) is an extension of the classical job shop scheduling problem which allows an operation to be processed by any machine from a given set. The problem is to assign each operation to a machine and to order the operations on the machine...