Initial Results from Beam Commissioning of the Lhc Beam Dump System

نویسندگان

  • B. Goddard
  • I. Agapov
  • E. Carlier
  • L. Ducimetière
  • E. Gallet
  • M. Gyr
  • L. Jensen
  • R. Jones
  • V. Kain
  • T. Kramer
  • M. Lamont
  • M. Meddahi
  • V. Mertens
  • T. Risselada
  • J. Uythoven
  • J. Wenninger
  • W. Weterings
چکیده

Initial commissioning of the LHC beam dump system with beam took place in August and September 2008. The preparation, setting-up and the tests performed are described together with results of the extractions of beam into the dump lines. Analysis of the first detailed aperture measurements of the extraction channels and kicker performance derived from dilution sweep shapes are presented. The performance of the other equipment subsystems is summarised, in particular that of the dedicated dump system beam instrumentation.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Apertures in the Lhc Beam Dump System and Beam Losses during Beam Abort

The LHC beam dumping system (LBDS) is used to dispose accelerated protons and ions in a wide energy range from 450 GeV up to 7 TeV. An abort gap of 3 μs is foreseen to avoid sweeping particles through the LHC ring aperture. This paper gives a brief overview of the critical apertures in the extraction region and the two beam dump lines. MAD-X tracking studies have been made to investigate the im...

متن کامل

Design Aspects Related to the Reliability of the Control Architecture of the Lhc Beam Dump Kicker Systems

The LHC beam dump extraction kicker system consists per ring of 15 magnets and their pulse generators. Their task is to extract the beams on request, over the whole operational beam energy range and synchronously with the beam abort gap. This operation must be fail-safe to avoid damage to accelerator equipment by undesired beam losses. The control system of the LHC beam dump kickers will be bas...

متن کامل

Commissioning and First Performance of the Lhc Beam Instrumentation

This paper will outline the progress with LHC commissioning to date, detailing the performance achieved with all the main LHC beam instrumentation systems. It will include an overview of the beam loss system and its role in machine protection, along with that of the beam position system and its use for automatic orbit control. Results will be shown from the highly sensitive base band tune syste...

متن کامل

Challenges and Plans for Injection and Beam Dump

The injection and beam dumping systems of the LHC will need to be upgraded to comply with the requirements of operation with the HL-LHC beams. The elements of the injection system concerned are the fixed and movable absorbers which protect the LHC in case of an injection kicker error and the injection kickers themselves. The beam dumping system elements under study are the absorbers which prote...

متن کامل

Commissioning of the Lhc Low Level Rf System Remote Configuration Tools*

The LHC Low Level RF system (LLRF) is a complex multi-loop system used to regulate the superconductive cavity gap voltage as well as to reduce the impedance presented by RF stations to the beam. The RF system can have a profound impact on the stability of the beam; a mis-configured RF system has the potential of causing longitudinal instabilities, beam diffusion and beam loss. To configure the ...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2009