Construction began in 1995 on ISAC, a radioactive ion beam (RIB) and accelerator facility at TRIUMF that utilises the ISOL (on-line isotope separation) production method. ISAC includes: a new building, a beam line with adequate shielding to transport up to 100 uA of 500 MeV protons to two target/ion-source stations, remote handling facilities for the targets, a high-resolution mass-separator, linear accelerators and experimental facilities. The ISAC target/ion source station permits the production of nuclei far from stability over a large isotopic range with high luminosity. Ions from the target/ion-source can be transported at energies up to 60 keV through a low-resolution pre-separator magnet followed by a high-acceptance, high-resolution mass-separator magnet to a variety of low energy experimental stations. Alternatively, ions with q/A greater than or equal to 1/30 and an energy of 2 keV/amu can be bunched in the low energy beam transport line prior to a cw RFQ accelerator operating at 35 MHz. The 150 keV/amu beam from the RFQ is stripped and isotopes with a particular q/A greater than or equal to 1/6 are selected for acceleration in a DTL. The DTL is a separated function accelerator with five accelerating tanks and three split-ring bunchers operating cw at 105 MHz. The final energy will be variable from 0.15 to 1.5 MeV/amu. The accelerated beams will be used primarily for nuclear astrophysics studies. The beam commissioning of the proton beam line, target/ion source, mass separator and RFQ has started. The TRIUMF neutral atom trap (TRINAT) and a yield station began using the low energy ISAC beam in November 1998. The RFQ has accelerated stable ions up to 54 keV/amu. The first tank of the drift tube linac and the subsequent buncher have been commissioned at full rf power. Beam commissioning of the DTL is scheduled for the end of 1999. The full-energy RIB will become available for the DRAGON recoil spectrometer at the end of 2000. A new five-year plan that includes an upgrade of ISAC to permit acceleration of radioactive ions up to 6.5 MeV/amu for masses up to 150 amu has been presented for funding.
منابع مشابه
Isac at Triumf: Recent Achievements and Future Goals
The ISAC facility at TRIUMF is now routinely delivering record intensities of radioactive ions to low energy experiments (E ≤ 60 keV). The post-accelerator for ISAC includes a 35.4 MHz RF Quadrupole (RFQ) and a poststripper, 106.1 MHz variable energy drift tube linac (DTL) to accelerate ions to a final energy from 0.15 to 1.5 MeV/u. The RFQ has been fully commissioned and the DTL is being insta...
متن کاملCommissioning of the Francium Trapping Facility at TRIUMF
We report on the successful commissioning of the Francium Trapping Facility at TRIUMF. Large laser-cooled samples of francium are produced from a francium ion beam delivered by the ISAC radioactive ion beam facility. The ion beam is neutralized on an yttrium foil, which is subsequently heated to transfer the atoms into the magneto-optical trapping region. We have successfully trapped 207Fr, 209...
متن کاملBeam Delivery and Future Initiatives at the Isac Radioactive Ion Beam Facility*
The ISAC facility, located at TRIUMF, first began delivering radioactive ion beams (RIBs) in 1998, added post-accelerated beam capability in 2001, and is regarded as one of the premiere RIB facilities in the world. The existing constraints on RIBs of Z<83 and accelerated beams of A/q≤30 with energies limited to 5 MeV/u are being addressed. A charge-state booster for RIBs has been commissioned t...
متن کاملStatus Update on the Isac Control System
Implementation and commissioning of the EPICS based control system for the ISAC radioactive beam facility was completed. The target ion source, mass separator, and low-energy beam-lines started beam production for experiments. In parallel, controls for the accelerator system, a radio-frequency quadrupole followed by a drift-tube linac, and several high-energy beam-lines were implemented and com...
متن کاملAcceleration of Charge Bred Radioactive Ions at Triumf
Most ion sources at ISOL (isotope separation on-line) facilities can produce only singly charged ions but efficient post acceleration requires high charge states. For light ions this can be achieved by stripping after a first moderate acceleration but with heavy ions this is no longer possible and charge state breeding is necessary. The breeder should be able to work at a high efficiency for th...