Schedule generation schemes for the job-shop problem with sequence-dependent setup times: dominance properties and computational analysis
نویسندگان
چکیده
We consider the job-shop problem with sequence-dependent setup times. We focus on the formal definition of schedule generation schemes (SGSs) based on the semi-active, active, and non-delay schedule categories. We study dominance properties of the sets of schedules obtainable with each SGS. We show how the proposed SGSs can be used within single-pass and multi-pass priority rule based heuristics. We study several priority rules for the problem and provide a comparative computational analysis of the different SGSs on sets of instances taken from the literature. The proposed SGSs significantly improve previously best-known results on a set of hard benchmark instances.
منابع مشابه
A New Multi-objective Job Shop Scheduling with Setup Times Using a Hybrid Genetic Algorithm
This paper presents a new multi objective job shop scheduling with sequence-dependent setup times. The objectives are to minimize the makespan and sum of the earliness and tardiness of jobs in a time window. A mixed integer programming model is developed for the given problem that belongs to NP-hard class. In this case, traditional approaches cannot reach to an optimal solution in a reasonable...
متن کاملA Job Shop Scheduling Problem with Sequence-Dependent Setup Times Considering Position-Based Learning Effects and Availability Constraints
Sequence dependent set-up times scheduling problems (SDSTs), availability constraint and transportation times are interesting and important issues in production management, which are often addressed separately. In this paper, the SDSTs job shop scheduling problem with position-based learning effects, job-dependent transportation times and multiple preventive maintenance activities is studied. ...
متن کاملMinimizing the maximum tardiness and makespan criteria in a job shop scheduling problem with sequence dependent setup times
The job shop scheduling problem (JSP) is one of the most difficult problems in traditional scheduling because any job consists of a set operations and also any operation processes by a machine. Whereas the operation is placed in the machine, it is essential to be considering setup times that the times strongly depend on the various sequencing of jobs on the machines. This research is developed ...
متن کاملA fuzzy multi-objective linear programming approach for solving a new multi-objective job shop scheduling with sequence-dependent setup times
This paper presents a new mathematical model for a bi-objective job shop scheduling problem with sequence-dependent setup times that minimizes the weighted mean completion time and the weighted mean tardiness time. For solving this multi-objective model, we develop a fuzzy multi-objective linear programming (FMOLP) model. In this problem, a proposed FMOLP method is applied with respect to the o...
متن کاملA three-stage assembly flow shop scheduling problem with blocking and sequence-dependent set up times
This paper considers a three-stage assembly flowshop scheduling problem with sequence-dependent setup < /div> times at the first stage and blocking times between each stage in such a way that the weighted mean completion time and makespan are minimized. Obtaining an optimal solution for this type of complex, large-sized problem in reasonable computational time using traditiona...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید
ثبت ناماگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید
ورودعنوان ژورنال:
- Annals OR
دوره 138 شماره
صفحات -
تاریخ انتشار 2005