Robust execution strategies for project scheduling with unreliable resources and stochastic durations

نویسندگان

  • Na Fu
  • Hoong Chuin Lau
  • Pradeep Varakantham
چکیده

The Resource Constrained Project Scheduling Problem with minimum and maximum time lags (RCPSP/max) is a general model for resource scheduling in many real-world problems (such as manufacturing and construction engineering). We consider RCPSP/max problems where the durations of activities are stochastic and resources can have unforeseen breakdowns. Given a level of allowable risk, α, our mechanisms aim to compute the minimum robust makespan execution strategy. Robust makespan for an execution strategy is any makespan value that has a risk less than α. The risk for a makespan value, M given an execution strategy is the probability that a schedule instantiated from the execution strategy will not finish before M given the uncertainty over durations and resources. We make three key contributions: (a) Firstly, we provide an analytical evaluation of resource breakdowns and repairs on executions of activities; (b) We then incorporate such information into a local search framework and generate execution strategies that can absorb resource and durational uncertainties; and (c) Finally, to improve robustness of resulting strategies, we propose Resource Breakdown Aware Chaining procedure with three different metrics. This chaining procedure computes resource allocations by predicting the effect of breakdowns on robustness of generated strategies. Experiments show effectiveness of our proposed methods in providing more robust execution strategies under uncertainty. Na FU · Hoong Chuin LAU · Pradeep VARAKANTHAM E-mail: [email protected] E-mail: [email protected] E-mail: [email protected] School of Information Systems, Singapore Management University, 80 Stamford Road, 178902 Singapore

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Developing Robust Project Scheduling Methods for Uncertain Parameters

A common problem arising in project management is the fact that the baseline schedule is often disrupted during the project execution because of uncertain parameters. As a result, project managers are often unable to meet the deadline time of the milestones. Robust project scheduling is an effective approach in case of uncertainty. Upon adopting this approach, schedules are protected against po...

متن کامل

ROBUST RESOURCE-CONSTRAINED PROJECT SCHEDULING WITH UNCERTAIN-BUT-BOUNDED ACTIVITY DURATIONS AND CASH FLOWS II. SOUNDS OF SILENCE: A NEW SAMPLING-BASED HYBRID PRIMARY-SECONDARY CRITERIA HARMONY SEARCH METAHEURISTIC

In this paper, we present a new idea for robust project scheduling combined with a cost-oriented uncertainty investigation. The result of the new approach is a makespan minimal robust proactive schedule, which is immune against the uncertainties in the activity durations and which can be evaluated from a cost-oriented point of view on the set of the uncertain-but-bounded duration and cost param...

متن کامل

ROBUST RESOURCE-CONSTRAINED PROJECT SCHEDULING WITH UNCERTAIN-BUT-BOUNDED ACTIVITY DURATIONS AND CASH FLOWS I. A NEW SAMPLING-BASED HYBRID PRIMARY-SECONDARY CRITERIA APPROACH

This paper, we presents a new primary-secondary-criteria scheduling model for resource-constrained project scheduling problem (RCPSP) with uncertain activity durations (UD) and cash flows (UC). The RCPSP-UD-UC approach producing a “robust” resource-feasible schedule immunized against uncertainties in the activity durations and which is on the sampling-based scenarios may be evaluated from a cos...

متن کامل

A multi-objective resource-constrained project scheduling problem with time lags and fuzzy activity durations

The resource-constrained project scheduling problem is to find a schedule that minimizes the project duration subject to precedence relations and resource constraints. To further account for economic aspects of the project, one may add an objective of cash nature to the problem. In addition, dynamic nature and variations in real world are known to introduce uncertainties into data. Therefore, t...

متن کامل

Maximizing service level in a β-robust job shop scheduling model

In the realm of scheduling problems, different sources of uncertainty such as probabilistic durations of jobs or stochastic breakdowns of machines can arise. Given this, one highly desirable characteristic of an intelligent schedule is to bring better punctuality with less efficiency-loss because a dominant factor in customer appreciation is punctuality. It is also one of the most intangible to...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • J. Scheduling

دوره 18  شماره 

صفحات  -

تاریخ انتشار 2015