Management of Temporal Constraints for Factory Scheduling

نویسندگان

  • Claude Le Pape
  • Stephen F. Smith
چکیده

In this paper, we present constraint propagation techniques used in the OPIS scheduling system to update schedule descriptions and detect introduced inconsistencies. Our approach is summarized as follows: • A hierarchical model is used to represent resources and operations to be performed. Schedules are developed and maintained at different levels of precision which are explicitly associated with resources and operations; constraint propagation is correspondingly performed at different levels. • Various scheduling constraints are attached to resources and operations, and combined to derive time bound constraints. A description of the original constraints that collectively impose a bound is explicitly recorded. • Time bound constraints are maintained by an object-oriented propagation process: through messages, resources and operations communicate constraints and cooperate to compute time bounds. • When time bounds are inconsistent, their origins provide the information required to construct an appropriate description of the conflicting situation. This description provides OPIS with information needed to make reactive decisions.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

The Management of Job-Shop Scheduling Constraints in TOSCA

Production management involves planning, scheduling and control. Whereas mrp-ii systems have contributed greatly to production planning, detailed scheduling and control remain problematic and have proved a signi cant research challenge. tosca is a research and development programme which provides an overall framework for production planning, scheduling and control based around representations o...

متن کامل

Constraint Monitoring in TOSCA

The Job-Shop Scheduling Problem (JSSP) deals with the allocation of resources over time to factory operations. Allocations are subject to various constraints (e.g., production precedence relationships, factory capacity constraints, and limits on the allowable number of machine setups) which must be satisfied for a schedule to be valid. The identification of constraint violations and the monitor...

متن کامل

Using Theory of Constraints in Production Management and Scheduling (A Case Study)

In manufacturing institutes the only access way to maximum profit is identifying the production mix of the products based on the limitations such as policies and politics, demand and production processes. This study identifies the constraints of a tile-manufacturing company including constraints in its production and demand line using LINGO software version 15, and identifying production bottle...

متن کامل

Micro-opportunistic Scheduling the Micro-boss Factory Scheduler

A major challenge for research in production management is to develop new finite-capacity scheduling techniques and tools that (1) can account more precisely for actual production management constraints and objectives, (2) are better suited for handling production contingencies, and (3) allow the user to interactively manipulate the production schedule to reflect idiosyncratic constraints and p...

متن کامل

Development of Model and Algorithm for Depot Balancing Multi-Depot Vehicle Scheduling Problem Considering Depot Balancing

The main of multi-depot vehicle scheduling problem (MDVSP) is to schedule the timetabled trips using limited resources, optimally. The problem is very important in the management of the transportation systems. One of the most useful ways to better manage these systems is to consider the real conditions including depot balancing constraints. To normalize the number of vehicles departed from each...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 1987