The Stochastic Economic Lot Sizing Problem for Continuous Multi-Grade Production

نویسندگان

  • George Liberopoulos
  • Dimitrios G. Pandelis
  • Olympia Hatzikonstantinou
چکیده

We study a variant of the stochastic economic lot scheduling problem (SELSP) in which a single production facility must produce several different grades of a family of products to meet random stationary demand for each grade from a common finished-goods (FG) inventory buffer with limited storage capacity. Demand that can not be satisfied directly from inventory is lost. Raw material is always available, and the production facility continuously produces at a constant rate. When the facility is set up to produce a particular grade, the only allowable changeovers are from that grade to next lower or higher grade. All changeover times are constant and equal to each other. There is a changeover cost per changeover occasion, a spill-over cost per unit of product in excess whenever there is not enough space in the FG buffer to store the produced grade, and a lost-sales cost per unit short whenever there is not enough FG inventory to satisfy demand. We model the SELSP as a discrete-time Markov decision process (MDP), where in each time period the decision is whether to initiate a changeover to a neighboring grade or keep the set up of the production facility unchanged, based on the current state of the system which is defined by the current set up of the facility and the FG inventory levels of all the grades. The goal is to minimize the (long-run) expected average cost per period. For 2-and 3-grade problems, we numerically solve the exact MDP problem using the value iteration method. For problems with more than three grades, we develop a heuristic solution procedure which is based on approximating the original multi-grade problem by several 3-grade sub-problems and numerically solving each sub-problem using value iteration. We present numerical results for problem examples with 2-5 grades. For the 2-and 3-grade examples, we use the exact solution procedure to obtain insights into the structure of the optimal changeover policy. For the 4-and 5-grade examples, we compare the performance of the heuristic solution procedure against that of the exact procedure.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

OPTIMIZATION OF A PRODUCTION LOT SIZING PROBLEM WITH QUANTITY DISCOUNT

Dynamic lot sizing problem is one of the significant problem in industrial units and it has been considered by  many researchers. Considering the quantity discount in  purchasing cost is one of the important and practical assumptions in the field of inventory control models and it has been less focused in terms of stochastic version of dynamic lot sizing problem. In  this paper, stochastic dyn...

متن کامل

A Multi-level Capacitated Lot-sizing Problem with Safety Stock Deficit and Production Manners: A Revised Simulated Annealing

[1] Corresponding author e-mail: [email protected]   [1] Corresponding author e-mail: [email protected]   Lot-sizing problems (LSPs) belong to the class of production planning problems in which the availability quantities of the production plan are always considered as a decision variable. This paper aims at developing a new mathematical model for the multi-level ca...

متن کامل

JOINT ECONOMIC LOT SIZING PROBLEM IN A TWO ECHELON PRODUCTION SYSTEM WITH FINITE PRODUCTION RATE AND LEAD TIME

In this study, a two-echelon supplier-manufacturer system with finite production rate and lead time is proposed. It is assumed that shortage is not permitted and the lot size of manufacturer (second echelon) is m-factors of the lot size of supplier (first echelon) and supplier can supply the manufacturer’s lot size in several shipments in each cyc...

متن کامل

The Economic Lot Sizing Problem for Continuous Multi-grade Production with Stochastic demands

We study a variant of the Stochastic Economic Lot Scheduling Problem (SELSP) in which a single production facility must produce several grades to meet random stationary demand for each grade from a common finished-goods (FG) inventory buffer with limited storage capacity. Demand that can not be satisfied directly from inventory is lost. Raw material is always available, and the production facil...

متن کامل

A Multi-objective Mathematical Model for Sustainable Supplier Selection and Order Lot-Sizing under Inflation

Recently, scholars and practitioners have shown an increased interest in the field of sustainable supplier selection and order lot-sizing. While several studies have recently carried out on this field, far too little attention has been given to formulating a multi-objective model for the integrated problem of multi-period multi-product order lot-sizing and sustainable supplier selection under i...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2009