Apply Metaheuristic ANGEL to Schedule Multiple Projects with Resource-Constrained and Total Tardy Cost
نویسندگان
چکیده
In this paper the multiple projects resourceconstrained project scheduling problem is considered. Several projects are to be scheduled simultaneously with sharing several kinds of limited resources in this problem. Each project contains non-preemptive and deterministic duration activities which compete limited resources under resources and precedence constraints. Moreover, there are the due date for each project and the tardy cost per day that cause the penalty when the project cannot be accomplished before its due date. The objective is to find the schedules of the considered projects to minimize the total tardy cost subject to the resource and precedence constraints. Since the resource-constrained project scheduling problem has been proven to be NP-Hard, we cannot find a deterministic algorithm to solve this problem efficiently and metaheuristics or evolutionary algorithms are developed for this problem instead. The problem considered in this paper is harder than the original problem because the due date and tardy cost of a project are considered in addition. The metaheuristic method called ANGEL was applied to this problem. ANGEL combines ant colony optimization (ACO), genetic algorithm (GA) and local search strategy. In ANGEL, ACO and GA run alternately and cooperatively. ANGEL performs very well in the multiple projects resource-constrained project scheduling problem as revealed by the experimental results. Keywords—multiple project scheduling; resource-constrained project scheduling; ANGEL; ant colony optimization; genetic algorithms; local search; metaheuristics
منابع مشابه
ROBUST RESOURCE-CONSTRAINED PROJECT SCHEDULING WITH UNCERTAIN-BUT-BOUNDED ACTIVITY DURATIONS AND CASH FLOWS II. SOUNDS OF SILENCE: A NEW SAMPLING-BASED HYBRID PRIMARY-SECONDARY CRITERIA HARMONY SEARCH METAHEURISTIC
In this paper, we present a new idea for robust project scheduling combined with a cost-oriented uncertainty investigation. The result of the new approach is a makespan minimal robust proactive schedule, which is immune against the uncertainties in the activity durations and which can be evaluated from a cost-oriented point of view on the set of the uncertain-but-bounded duration and cost param...
متن کاملA hybrid GRASP algorithm for minimizing total weighted resource tardiness penalty costs in scheduling of project networks
In this paper, we consider scheduling of project networks under minimization of total weighted resource tardiness penalty costs. In this problem, we assume constrained resources are renewable and limited to very costly machines and tools which are also used in other projects and are not accessible in all periods of time of a project. In other words, there is a dictated ready date as well as a d...
متن کاملA Multi-Mode Resource-Constrained Optimization of Time-Cost Trade-off Problems in Project Scheduling Using a Genetic Algorithm
In this paper, we present a genetic algorithm (GA) for optimization of a multi-mode resource constrained time cost trade off (MRCTCT) problem. The proposed GA, each activity has several operational modes and each mode identifies a possible executive time and cost of the activity. Beyond earlier studies on time-cost trade-off problem, in MRCTCT problem, resource requirements of each execution mo...
متن کاملFlexible resource management and its effect on project cost and duration
In practice, most projects result in cost overruns and schedule slippage due to poor resource management. This paper presents an approach that aims at reducing project duration and costs by empowering project managers to assess different scenarios. The proposed approach addresses combinatorial modes for tasks, multi-skilled resources, and multiple calendars for resources. A case study reported ...
متن کاملForecasting Final Schedule and Cost of Projects by Using Statistical and Mathematical Method
Earned value management (EVM) has prepared some methods to forecast final costs of projects. These methods were not developed since the start of formation and were gradually completed, of course with one exception that is its authenticity, they are still remained unchanged. At the present time EVM guide does not apply from schedule indices to forecast schedule for completion of project and ...