New Heuristics for No-Wait Flowshops with Performance Measures of Makespan and Mean Completion Time
نویسندگان
چکیده
The m-machine no-wait flowshop scheduling problem is addressed by taking into account two performance measures of makespan and mean completion time. The objective is to minimize makespan such that mean completion time is less than a certain value. A dominance relation is provided for a special case of the problem. Moreover, two new heuristics are proposed in this paper. Computational analysis indicates that one of the proposed heuristics (eSA) reduces the error of the previously best known heuristic for the problem (HH1) by 70% while the computational time of HH1 is 30% more than that of eSA. Furthermore, the computational analysis also indicates that the other proposed heuristic (eHH) reduces the error of HH1 by 80% while both eHH and HH1 have the same computational time. All the results have been statistically verified.
منابع مشابه
َA Multi-objective simulated annealing algorithm to solving flexible no-wait flowshop scheduling problems with transportation times
This paper deals with a bi-objective hybrid no-wait flowshop scheduling problem minimizing the makespan and total weighted tardiness, in which we consider transportation times between stages. Obtaining an optimal solution for this type of complex, large-sized problem in reasonable computational time by using traditional approaches and optimization tools is extremely difficult. This paper presen...
متن کاملSolving Re-entrant No-wait Flexible Flowshop Scheduling Problem; Using the Bottleneck-based Heuristic and Genetic Algorithm
In this paper, we study the re-entrant no-wait flexible flowshop scheduling problem with makespan minimization objective and then consider two parallel machines for each stage. The main characteristic of a re-entrant environment is that at least one job is likely to visit certain stages more than once during the process. The no-wait property describes a situation in which every job has its own ...
متن کاملAlgorithms for no-wait flowshops with total completion time subject to makespan
The m-machine no-wait flowshop scheduling problem, with the objective of minimizing total completion time subject to the constraint that makespan has to be less than or equal to a certain value, is addressed in this paper. First, an algorithm is proposed to find an upper bound on the makespan in case the upper bound is not given or unknown. Given the upper bound on makespan, a proposed algorith...
متن کاملNo-wait flowshops with bicriteria of makespan and maximum lateness
In this work we study a flowshop scheduling problem in which jobs are not allowed to wait in-between machines, a situation commonly referred to as no-wait. The concerned criterion is to minimize a weighted sum of makespan and maximum lateness. A dominance relation for the case of three-machine is presented and evaluated by experimental designs. Several heuristics and local search methods are pr...
متن کاملComparing Mixed-Integer and Constraint Programming for the No-Wait Flow Shop Problem with Due Date Constraints
The impetus for this research was examining a flow shop problem in which tasks were expected to be successively carried out with no time interval (i.e., no wait time) between them. For this reason, they should be completed by specific dates or deadlines. In this regard, the efficiency of the models was evaluated based on makespan. To solve the NP-Hard problem, we developed two mathematical mode...