A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

نویسندگان

  • W. Na
  • P. Wuliang
چکیده

Since there are obvious uncertainties in task duration, the uncertainty will be passed step by step due to the precedence relationships among tasks. Therefore, one should pay attention to the robustness of project plan when scheduling the project. In this paper, the project plan robustness is evaluated as the probability of completing the project in the planning duration, the Monte Carlo method is used to simulate the practical implementation of the project plan considering the characteristics of task duration distribution, and thus a complete estimation approach for project plans is presented. This approach can help project managers to determine the project duration risk and identify the key tasks that influence the project plan robustness seriously at the beginning of project planning.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

A COMPARATIVE MODEL OF EVM AND PROJECT’S SCHEDULE RISK ANALYSIS USING MONTE CARLO SIMULATION

<span style="color: #000000; font-family: Tahoma, sans-serif; font-size: 13px; font-style: normal; font-variant: normal; font-weight: normal; letter-spacing: normal; line-height: normal; orphans: auto; text-align: justify; text-indent: 0px; text-transform: none; white-space: normal; widows: auto; word-spacing: 0px; -webkit-text-stroke-width: 0px; display: inline !important; float: none; backgro...

متن کامل

A COMPARATIVE MODEL OF EVM AND PROJECT’S SCHEDULE RISK ANALYSIS USING MONTE CARLO SIMULATION

<span style="color: #000000; font-family: Tahoma, sans-serif; font-size: 13px; font-style: normal; font-variant: normal; font-weight: normal; letter-spacing: normal; line-height: normal; orphans: auto; text-align: justify; text-indent: 0px; text-transform: none; white-space: normal; widows: auto; word-spacing: 0px; -webkit-text-stroke-width: 0px; display: inline !important; float: none; backgro...

متن کامل

Establishing Control Limits on Time Performance Indicators of Projects through Monte Carlo Simulation and Earned Duration Management

Earned Duration Management (EDM) method has been developed to enhance Earned Value Management and to solve some of its problems, such as separation of measuring time and cost dimensions. By providing performance indicators, this method makes it possible for managers to accurately measure the progress of a project and to calculate the time and cost required to complete it. Nevertheless, the acce...

متن کامل

Project Time and Cost Forecasting using Monte Carlo simulation and Artificial Neural Networks

The aim of this study is to present a new method to predict project time and cost under uncertainty. Assuming that what happens in projects implementation which is expressed in the form of Earned Value Management (EVM) indicators is primarily related to the nature of randomness or unreliability, in this study, by using Monte Carlo simulation, and assuming a specific distribution for the time an...

متن کامل

Application of Monte Carlo Simulation in the Assessment of European Call Options

In this paper, the pricing of a European call option on the underlying asset is performed by using a Monte Carlo method, one of the powerful simulation methods, where the price development of the asset is simulated and value of the claim is computed in terms of an expected value. The proposed approach, applied in Monte Carlo simulation, is based on the Black-Scholes equation which generally def...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:

دوره   شماره 

صفحات  -

تاریخ انتشار 2015