Robust Local Search for Solving RCPSP/max with Durational Uncertainty

نویسندگان

  • Na Fu
  • Hoong Chuin Lau
  • Pradeep Varakantham
  • Fei Xiao
چکیده

Scheduling problems in manufacturing, logistics and project management have frequently been modeled using the framework of Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max). Due to the importance of these problems, providing scalable solution schedules for RCPSP/max problems is a topic of extensive research. However, all existing methods for solving RCPSP/max assume that durations of activities are known with certainty, an assumption that does not hold in real world scheduling problems where unexpected external events such as manpower availability, weather changes, etc. lead to delays or advances in completion of activities. Thus, in this paper, our focus is on providing a scalable method for solving RCPSP/max problems with durational uncertainty. To that end, we introduce the robust local search method consisting of three key ideas: (a) Introducing and studying the properties of two decision rule approximations used to compute start times of activities with respect to dynamic realizations of the durational uncertainty; (b) Deriving the expression for robust makespan of an execution strategy based on decision rule approximations; and (c) A robust local search mechanism to efficiently compute activity execution strategies that are robust against durational uncertainty. Furthermore, we also provide enhancements to local search that exploit temporal dependencies between activities. Our experimental results illustrate that robust local search is able to provide robust execution strategies efficiently.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Towards Finding Robust Execution Strategies for RCPSP/max with Durational Uncertainty

Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max) have been studied extensively in the literature. However, the more realistic RCPSP/max problems – ones where durations of activities are not known with certainty – have received scant interest and hence are the main focus of the paper. Towards addressing the significant computational complexity invol...

متن کامل

Robust Partial Order Schedules for RCPSP/max with Durational Uncertainty

In this work, we consider RCPSP/max with durational uncertainty. We focus on computing robust Partial Order Schedules (or, in short POS) which can be executed with risk controlled feasibility and optimality, i.e., there is stochastic posteriori quality guarantee that the derived POS can be executed with all constraints honored and completion before robust makespan. To address this problem, we p...

متن کامل

A Proactive Sampling Approach to Project Scheduling under Uncertainty

Uncertainty in activity durations is a key characteristic of many real world scheduling problems in manufacturing, logistics and project management. RCPSP/max with durational uncertainty is a general model that can be used to represent durational uncertainty in a wide variety of scheduling problems where there exist resource constraints. However, computing schedules or execution strategies for ...

متن کامل

Robust execution strategies for project scheduling with unreliable resources and stochastic durations

The Resource Constrained Project Scheduling Problem with minimum and maximum time lags (RCPSP/max) is a general model for resource scheduling in many real-world problems (such as manufacturing and construction engineering). We consider RCPSP/max problems where the durations of activities are stochastic and resources can have unforeseen breakdowns. Given a level of allowable risk, α, our mechani...

متن کامل

Robust Local Search and Its Application to Generating Robust Schedules

In this paper, we propose an extended local search framework to solve combinatorial optimization problems with data uncertainty. Our approach represents a major departure from scenario-based or stochastic programming approaches often used to tackle uncertainty. Given a value 0 < ≤ 1, we are interested to know what the robust objective value is, i.e. the optimal value if we allow an chance of no...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • J. Artif. Intell. Res.

دوره 43  شماره 

صفحات  -

تاریخ انتشار 2012