This paper considers the problem of scheduling n jobs on a single machine. A fixed processing time and an execution interval are associated with each job. Preemption is not allowed. The objective is to find a feasible job sequence that minimizes the number of tardy jobs. On the basis of an original mathematical integer programming formulation, this paper shows how good-quality lower and upper bounds can be computed. Numerical experiments are provided for assessing the proposed approach.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Minimizing the Number of Tardy Jobs in the Single Machine Scheduling Problem under Bimodal Flexible and Periodic Availability Constraints

In single machine scheduling problems with availability constraints, machines are not available for one or more periods of time. In this paper, we consider a single machine scheduling problem with flexible and periodic availability constraints. In this problem, the maximum continuous working time for each machine increases in a stepwise manner with two different values allowed. Also, the durati...

متن کامل

Minimizing the number of tardy jobs in single machine scheduling using MIP

This paper considers the problem of scheduling n jobs on a single machine. A fixed processing time and an execution interval are associated with each job. Preemption is not allowed. The objective is to find a feasible job sequence that minimizes the number of tardy jobs. On the basis of an original mathematical integer programming formulation, this paper shows how both good-quality lower and up...

متن کامل

Solving the Single Machine Problem with Quadratic Earliness and Tardiness Penalties

  Nowadays, scheduling problems have a considerable application in production and service systems. In this paper, we consider the scheduling of n jobs on a single machine assuming no machine idleness, non-preemptive jobs and equal process times. In many of previous researches, because of the delivery dalays and holding costs, earliness and tardiness penalties emerge in the form of linear combin...

متن کامل

A branch and bound algorithm to minimize the total weighted number of tardy jobs and delivery costs with late deliveries for a supply chain scheduling problem

In this paper, we study a supply chain scheduling problem that simultaneously considers production scheduling and product delivery.  jobs have to be scheduled on a single machine and delivered to  customers for further processing in batches. The objective is to minimize the sum of the total weighted number of tardy jobs and the delivery costs. In this paper, we present a heuristic algorithm (HA...

متن کامل

Minimizing Makespan with Start Time Dependent Jobs in a Two Machine Flow Shop

[if gte mso 9]> The purpose of this paper is to consider the problem of scheduling a set of start time-dependent jobs in a two-machine flow shop, in which the actual processing times of jobs increase linearly according to their starting time. The objective of this problem is to minimize the makespan. The problem is known to be NP-hardness[ah1] ; therefore, there is no polynomial-time algorithm...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • RAIRO - Operations Research

دوره 47  شماره 

صفحات  -

تاریخ انتشار 2013