This paper reconsiders the PERT scheduling problem when information about task duration is incomplete. We model uncertainty on task durations by intervals. With this problem formulation, our goal is to assert possible and necessary criticality of the different tasks and to compute their possible earliest starting dates, latest starting dates and floats. This paper puts together various results and provides a complete solution to the problem. We present the complexity results of all considered subproblems and efficient algorithms to solve them.
منابع مشابه
An Algorithm to Obtain Possibly Critical Paths in Imprecise Project Networks
We consider criticality in project networks having imprecise activity duration times. It is well known that finding all possibly critical paths of an imprecise project network is an NP-hard problem. Here, based on a method for finding critical paths of crisp networks by using only the forward recursion of critical path method, for the first time an algorithm is proposed which can find all pos...
متن کاملProposing a Robust Model of Interval Data Envelopment Analysis to Performance Measurement under Double Uncertainty Situations
It is very necessary to consider the uncertainty in the data and how to deal with it when performance measurement using data envelopment analysis. Because a little deviation in the data can lead to a significant change in the performance results. However, in the real world and in many cases, the data is uncertain. Interval data envelopment analysis is one of the most widely used approaches to d...
متن کاملTime Online Calendar Ambient Acoustical Signal Desktop Activity Inspection Interval
We introduce utility-directed procedures for mediating the ow of potentially distracting alerts and communications to computer users. We present models and inference procedures that balance the context-sensitive costs of deferring alerts with the cost of interruption. We describe the challenge of reasoning about such costs under uncertainty via an analysis of user activity and the content of no...
متن کاملA New Version of Earned Value Analysis for Mega Projects Under Interval-valued Fuzzy Environment
The earned value technique is a crucial and important technique in analysis and control the performance and progress of mega projects by integrating three elements of them, i.e., time, cost and scope. This paper proposes a new version of earned value analysis (EVA) to handle uncertainty in mega projects under interval-valued fuzzy (IVF)-environment. Considering that uncertainty is very common i...
متن کاملCriticality analysis in activity networks under incomplete information
A review of the main results obtained by the authors concerning analysis of networks with imprecise activity duration times, with a stress on the analysis of criticality, is presented.
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
عنوان ژورنال:
- J. Scheduling
دوره 13 شماره
صفحات -
تاریخ انتشار 2010