Makespan minimization of multi-slot just-in-time scheduling on single and parallel machines

نویسندگان

  • Dariusz Dereniowski
  • Wieslaw Kubiak
چکیده

The paper addresses the problem of multi-slot just-in-time scheduling. Unlike the existing literature on this subject, it studies a more general criteria – the minimization of schedule makespan rather than the minimization of the number of slots used by schedule. It gives an O(n log n)-time optimization algorithm for the single machine problem. For arbitrary number of m > 1 identical parallel machines it presents an O(n logn)-time optimization algorithm for the case when the processing time of each job does not exceed its due date time. For a general case on m > 1 machines it proposes a polynomial time constant factor approximation algorithm.

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Solving a New Multi-objective Unrelated Parallel Machines Scheduling Problem by Hybrid Teaching-learning Based Optimization

This paper considers a scheduling problem of a set of independent jobs on unrelated parallel machines (UPMs) that minimizesthe maximum completion time (i.e., makespan or ), maximum earliness ( ), and maximum tardiness ( ) simultaneously. Jobs have non-identical due dates, sequence-dependent setup times and machine-dependentprocessing times. A multi-objective mixed-integer linear programmi...

متن کامل

حل مسأله زمان‌بندی کار کارگاهی چندهدفی انعطاف‌پذیرِ پویا به وسیله الگوریتم ژنتیک توسعه‌یافته

In this paper, Multi-Objective Flexible Job-Shop scheduling with Parallel Machines in Dynamic manufacturing environment (MO-FDJSPM) is investigated. Moreover considering dynamical job-shop environment (jobs arrived in non-zero time), It contains two kinds of flexibility which is effective for improving operational manufacturing systems. The non-flexibility leads to scheduling program which have...

متن کامل

Fuzzy Programming for Parallel Machines Scheduling: Minimizing Weighted Tardiness/Earliness and Flow Time through Genetic Algorithm

Appropriate scheduling and sequencing of tasks on machines is one of the basic and significant problems that a shop or a factory manager encounters; this is why in recent decades extensive studies have been done on scheduling issues. One type of scheduling problems is just-in-time (JIT) scheduling and in this area, motivated by JIT manufacturing, this study investigates a mathematical model for...

متن کامل

A bi-objective model for a scheduling problem of unrelated parallel batch processing machines with fuzzy parameters by two fuzzy multi-objective meta-heuristics

This paper considers a bi-objective model for a scheduling problem of unrelated parallel batch processing machines to minimize the makespan and maximum tardiness, simultaneously. Each job has a specific size and the data corresponding to its ready time, due date and processing time-dependent machine are uncertain and determined by trapezoidal fuzzy numbers. Each machine has a specific capacity,...

متن کامل

Bi-objective Optimization for Just in Time Scheduling: Application to the Two-Stage Assembly Flow Shop Problem

This paper considers a two-stage assembly flow shop problem (TAFSP) where m machines are in the first stage and an assembly machine is in the second stage. The objective is to minimize a weighted sum of earliness and tardiness time for n available jobs. JIT seeks to identify and eliminate waste components including over production, waiting time, transportation, inventory, movement and defective...

متن کامل

ذخیره در منابع من


  با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

ثبت نام

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

عنوان ژورنال:
  • J. Scheduling

دوره 13  شماره 

صفحات  -

تاریخ انتشار 2010