A solution approach for optimizing long- and short-term production scheduling at LKAB's Kiruna mine
نویسندگان
چکیده
We present a mixed-integer program to schedule longand short-term production at LKAB’s Kiruna mine, an underground sublevel caving mine located in northern Sweden. The model minimizes deviations from monthly preplanned production quantities while adhering to operational constraints. Because of the mathematical structure of the model and its moderately large size, instances spanning a time horizon of more than a year or two tend to be intractable. We develop an optimization-based decomposition heuristic that, on average, obtains better solutions faster than solving the model directly. We show that for realistic data sets, we can generate solutions with deviations that comprise about 3%-6% of total demand in about a third of an hour.
منابع مشابه
Implementing a Production Schedule at LKAB's Kiruna Mine
LKAB’s Kiruna Mine, located in northern Sweden, produces about 24 million tons of iron ore yearly using an underground mining method known as sublevel caving. To efficiently run the mills that process the iron ore, the mine must deliver planned quantities of three ore types. We used mixed-integer programming to schedule Kiruna’s operations, specifically, which production blocks to mine and when...
متن کاملA Comprehensive Study of Several Meta-Heuristic Algorithms for Open-Pit Mine Production Scheduling Problem Considering Grade Uncertainty
It is significant to discover a global optimization in the problems dealing with large dimensional scales to increase the quality of decision-making in the mining operation. It has been broadly confirmed that the long-term production scheduling (LTPS) problem performs a main role in mining projects to develop the performance regarding the obtainability of constraints, while maximizing the whole...
متن کاملResilient Decision Making in Open Pit Short-term Production Planning in Presence of Geologic Uncertainty
Short-term production plans are the basis for operational mine production schedules. They concentrate on making long-term mine plans operationally feasible. Furthermore, some variables such as ore grade and tonnage govern mine production systems and cause uncertainty in the supply of raw materials to the mills. Due to the quality variation of material, short-term production optimization is an u...
متن کاملAn imperialist competitive algorithm for solving the production scheduling problem in open pit mine
Production scheduling (planning) of an open-pit mine is the procedure during which the rock blocks are assigned to different production periods in a way that the highest net present value of the project achieved subject to operational constraints. The paper introduces a new and computationally less expensive meta-heuristic technique known as imperialist competitive algorithm (ICA) for long-term...
متن کاملیکپارچه سازی برنامهریزی و زمانبندی تولید در صنایع فرآیندی چند محصولی با سیستم تولیدی پیوسته
One of the main elements of each supply chain is production. Production planning in multi-products process industries in which products are subjected to the complicated operational constraints is a very hard work because production of computed optimal volume should be compatible with operation scheduling constraints of production system. Thus, integration idea has been proposed for required d...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید
ثبت ناماگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید
ورودعنوان ژورنال:
- European Journal of Operational Research
دوره 211 شماره
صفحات -
تاریخ انتشار 2011