Scheduling Maintenance Activities of Electric Power Transmission Networks Using an Hybrid Constraint Method
نویسندگان
چکیده
In this paper we present a Constraint Logic Programming (CLP) based model, and hybrid solving method for the Scheduling of Maintenance Activities in the Power Transmission Network. The model distinguishes from others not only because of its completeness but also by the way it models and solves the Electric Constraints. Specifically we present a efficient filtering algorithm for the Electrical Constraints. Furthermore, the solving method improves the pure CLP methods efficiency by integrating a type of Local Search technique with CLP. To test the approach we compare the method results with another method using a 24 bus network, which considerers 42 tasks and 24 maintenance periods.
منابع مشابه
Reliability Based Optimal Preventive Maintenance Policy for High Voltage Circuit Breakers in Power Plants
Electric power industry have always try to provide reliable electricity to customers and at the same time decrease system costs. High Voltage circuit-breakers are an essential part of the power network. This study has developed a maintenance and replacement scheduling model for high voltage circuit- breakers that minimize maintenance costs while maintaining the acceptable reliability. This mo...
متن کاملHybrid Constraint Algorithm for the Maintenance Scheduling of Electric Power Units
Maintenance scheduling of generating units is an important problem of power systems operation. Among different approaches to this problem it seams that Constraint Programming (CP) based ones are the most flexible, despite some lack of efficiency. In this paper a hybrid CP method, named Guided Constraint Search is presented. The method combines ideas from Guided Local Search with CP in order to ...
متن کاملCost and Environmental Pollution Reduction Based on Scheduling of Power Plants and Plug-in Hybrid Electric Vehicles
There has been a global effort to reduce the amount of greenhouse gas emissions. In an electric resource scheduling, emission dispatch and load economic dispatch problems should be considered. Using renewable energy resources (RESs), especially wind and solar, can be effective in cutting back emissions associated with power system. Further, the application of electric vehicles (EV) capable of b...
متن کاملMulti-objective Optimization of Hybrid Electric Vehicle Equipped with Power-split Continuously Variable Transmission
This paper aims to find the efficient state of hybrid electric vehicle (HEV) by simultaneous optimization of the control strategy and the power train. The power transmission employed in this vehicle is a power-split continuously variable transmission (CVT) which uses several fixed ratio mechanisms. After describing this transmission, the rules of electric assist control strategy are introduced....
متن کاملThree Hybrid Metaheuristic Algorithms for Stochastic Flexible Flow Shop Scheduling Problem with Preventive Maintenance and Budget Constraint
Stochastic flexible flow shop scheduling problem (SFFSSP) is one the main focus of researchers due to the complexity arises from inherent uncertainties and also the difficulty of solving such NP-hard problems. Conventionally, in such problems each machine’s job process time may encounter uncertainty due to their relevant random behaviour. In order to examine such problems more realistically, fi...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
عنوان ژورنال:
دوره شماره
صفحات -
تاریخ انتشار 2007