W propose a cooperation method between constraint programming and integer programming to compute lower bounds for the resource-constrained project scheduling problem (RCPSP). The lower bounds are evaluated through linear-programming (LP) relaxations of two different integer linear formulations. Efficient resource-constraint propagation algorithms serve as a preprocessing technique for these relaxations. The originality of our approach is to use additionally some deductions performed by constraint propagation, and particularly by the shaving technique, to derive new cutting planes that strengthen the linear programs. Such new valid linear inequalities are given in this paper, as well as a computational analysis of our approach. Through this analysis, we also compare the two considered linear formulations for the RCPSP and confirm the efficiency of lower bounds computed in a destructive way.
منابع مشابه
A New Bi-Objective Model for a Multi-Mode Resource-Constrained Project Scheduling Problem with Discounted Cash Flows and four Payment Models
The aim of a multi-mode resource-constrained project scheduling problem (MRCPSP) is to assign resource(s) with the restricted capacity to an execution mode of activities by considering relationship constraints, to achieve pre-determined objective(s). These goals vary with managers or decision makers of any organization who should determine suitable objective(s) considering organization strategi...
متن کاملResource Constrained Project Scheduling with Material Ordering: Two Hybridized Meta-Heuristic Approaches (TECHNICAL NOTE)
Resource constrained project scheduling problem (RCPSP) is mainly investigated with the objective of either minimizing project makespan or maximizing project net present value. However, when material planning plays a key role in a project, the existing models cannot help determining material ordering plans to minimize material costs. In this paper, the RCPSP incorporated with the material order...
متن کاملThe preemptive resource-constrained project scheduling problem subject to due dates and preemption penalties: An integer programming approach
Extensive research has been devoted to resource constrained project scheduling problem. However, little attention has been paid to problems where a certain time penalty must be incurred if activity preemption is allowed. In this paper, we consider the project scheduling problem of minimizing the total cost subject to resource constraints, earliness-tardiness penalties and preemption penalties, ...
متن کاملA multi-objective resource-constrained project scheduling problem with time lags and fuzzy activity durations
The resource-constrained project scheduling problem is to find a schedule that minimizes the project duration subject to precedence relations and resource constraints. To further account for economic aspects of the project, one may add an objective of cash nature to the problem. In addition, dynamic nature and variations in real world are known to introduce uncertainties into data. Therefore, t...
متن کاملOptimizing a bi-objective preemptive multi-mode resource constrained project scheduling problem: NSGA-II and MOICA algorithms
The aim of a multi-mode resource-constrained project scheduling problem (MRCPSP) is to assign resource(s) with the restricted capacity to an execution mode of activities by considering relationship constraints, to achieve pre-determined objective(s). These goals vary with managers or decision makers of any organization who should determine suitable objective(s) considering organization strategi...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
عنوان ژورنال:
- INFORMS Journal on Computing
دوره 17 شماره
صفحات -
تاریخ انتشار 2005