Exploration and Grouting of Large-Scale Water Capsule in the Fault Fracture Zone of Yonglian Tunnel
نویسندگان
چکیده
A large-scale water capsule was formed after 8 times inrush of mud and water in Yonglian tunnel. The capsule seriously inhabited the construction of the tunnel. By combining with the geological conditions in tunnel site, the causes and characteristics of the water capsule were analyzed. Its spatial location and size were explorated by comprehensive exploration methods. In order to control the water capsule, the treatment scheme composed by full-face curtain grouting in left tunnel and decompression by drainage in right tunnel was made, and the composite and controlling grouting methods were proposed. The composite and controlling grouting technology was applied in the treatment. It was composed by grouting parameters selection, grouting material and technology optimization by means of numerical simulation, model experiment and SEM microscopic experiment. By means of the grouting effect examination methods including P-Q-t curve, examination holes, surrounding rock deformation monitoring and excavation, the water capsule was proved to be treated successfully. The engineering case provides a reference for the similar engineering to some extent.
منابع مشابه
Tunnel Rehabilitation in Fault Zone Using Sequential Joints Method- Case Study: Karaj Water Conveyance Tunnel
The lining structure of Tunnel Boring Machine (TBM) excavated tunnels is composed of series of precast Reinforced Concrete (RC) pieces which are called segment. At the present paper, a novel method is introduced for seismic retrofitting of segmental tunnels located at active fault zones in rock environment with case study of Amirkabir dam to Tehran water transfer tunnel (Karadj tunnel). The mai...
متن کاملPredicting the Occurrence of Hydraulic Fracture in Grouting Operations Based on the Pressure in the Penetrated Cement Grout
Cement grouting is an operation often carried out to consolidate and seal the rock mass in dam sites and tunnels. The quality and efficiency of a grouting operation depends on various factors such as water take, grout properties and grouting pressure. One of the parameters which have the highest effect is pressure since the application of excessive pressure causes the hydraulic fracture phenome...
متن کاملTunnel design and construction process in difficult ground conditions with Analysis of Controlled Deformations (ADECO) approach; a Case Study
The 10.6 km long Sabzkuh water conveyance tunnel is currently under construction in High Zagros structural zone, located in western Iran, has used conventional (in section T1) and mechanized (in section T2) methods. The section T1 of the tunnel driven through alluvial geological units with great complexity in an area high potential for sliding and water-bearing fault which has made the excavati...
متن کاملNumerical Modelling of Backfill Grouting Approaches in EPB Tunneling
One of the main issues involved during tunnel construction with tunnel boring machines is the tail gap grouting. This gap is between the external diameter of tunnel lining and the excavation boundary that is filled with high-pressure grouting materials. In this work, three different approaches of gap grouting modeling in the FLAC3D software are investigated with a special attention to the...
متن کامل3D stochastic rock fracture modeling related to strike-slip faults
Fault zones and fault-related fracture systems control the mechanical behaviors and fluid-flow properties of the Earth’s crust. Furthermore, nowadays, modeling is being increasingly used in order to understand the behavior of rock masses, and to determine their characteristics. In this work, fault zones and fracture patterns are reviewed, and also comprehensive studies are carried out on the fr...
متن کامل