developing project scheduling model with makespan and robustness objectives

نویسندگان

ایمان بساق زاده

دانشگاه صنعتی اصفهان سید رضا حجازی

دانشگاه صنعتی اصفهان امیر موسی احسان

دانشگاه صنعتی شریف

چکیده

the research on project scheduling has widely expanded over the last few decades. the vast majority of these research efforts focus on exact and suboptimal procedures for constructing a workable schedule, assuming complete information and a static deterministic problem environment. project activities are scheduled subject to both technological precedence constraints and resource constraints, mostly under the objective of minimizing the project duration. the resulting schedule serves as the baseline for the execution of the project. during execution, however, the project is subject to considerable uncertainty, which may lead to numerous schedule disruptions. it is surprising to see that, given the large amount of projects that have finished late during the last decades, management still fails to quote accurate project due dates. this is problematic because virtually all organizations use their project plans not only as tools with which to manage the projects, but also as a foundation to make delivery commitments to clients. therefore, a vitally important purpose of project plans and effective scheduling methods is to enable organizations to estimate completion dates of the corresponding projects. a project schedule also serves as a baseline for material procurement, contacts with subcontractors, coordination of internal resources and corrective actions the ultimate goal which is more akin to deterministic scheduling, is to make scheduling and resource allocation decisions that will allow quoting a due date that should be as low as possible. such optimizations decisions need not only be taken before the project is actually started, but also scheduling and resource allocation should also be able during project execution in order protect promised dates from any sources of uncertainty that may occur. additionally, if advance knowledge about the nature of the uncertainty in the project is available, it is desirable that the project schedule be robust to disruptions that may arise. one of the important approaches in this issue is constructing robust project schedule. generally, this approach tries to construct robust project baseline schedule by considering uncertainty in such a way that any variations cannot make disruption in it as far as possible. in this article, we introduce the concept of schedule robustness and then we develop a bi-objective resource constrained project scheduling model. we consider the objectives of robustness maximization along with makespan minimization. then, we present a tabu search algorithm that operates on surrogate functions. this algorithm is developed in order to generate an approximate set of efficient solutions. many random project scheduling problems are generated, and then solved by the algorithm. finally, the efficiency of the algorithm and the robustness surrogate functions are evaluated by simulation. finally, the results show efficiency of the algorithm and developed surrogate function.

برای دانلود باید عضویت طلایی داشته باشید

برای دانلود متن کامل این مقاله و بیش از 32 میلیون مقاله دیگر ابتدا ثبت نام کنید

اگر عضو سایت هستید لطفا وارد حساب کاربری خود شوید

منابع مشابه

Developing Robust Project Scheduling Methods for Uncertain Parameters

A common problem arising in project management is the fact that the baseline schedule is often disrupted during the project execution because of uncertain parameters. As a result, project managers are often unable to meet the deadline time of the milestones. Robust project scheduling is an effective approach in case of uncertainty. Upon adopting this approach, schedules are protected against po...

متن کامل

A stochastic model for project selection and scheduling problem

Resource limitation in zero time may cause to some profitable projects not to be selected in project selection problem, thus simultaneous project portfolio selection and scheduling problem has received significant attention. In this study, budget, investment costs and earnings are considered to be stochastic. The objectives are maximizing net present values of selected projects and minimizing v...

متن کامل

A Multi-objective optimization model for project scheduling with time-varying resource requirements and capacities

Proper and realistic scheduling is an important factor of success for every project. In reality, project scheduling often involves several objectives that must be realized simultaneously, and faces numerous uncertainties that may undermine the integrity of the devised schedule. Thus, the manner of dealing with such uncertainties is of particular importance for effective planning. A realistic sc...

متن کامل

A tropical optimization problem with application to project scheduling with minimum makespan

We consider a multidimensional optimization problem in the framework of tropical mathematics. The problem is formulated to minimize a nonlinear objective function that is defined on vectors in a finitedimensional semimodule over an idempotent semifield and calculated by means of multiplicative conjugate transposition. We offer two complete direct solutions to the problem. The first solution con...

متن کامل

8.1 Makespan Scheduling

Definition 8.1.1 Let P = ∑ i∈J Pi. Clearly 1 ≤ OPT ≤ P . Since 1 ≤ OPT ≤ P , if we have access to a (1 + )-relaxed decision procedure we can use it O(logP ) times to do a binary search on different values of T (between 1 and P ) to find a (1 + )approximation. Since logP is polynomial in the input size, if the relaxed decision procedure runs in polynomial time then we have a (1 + )-approximation...

متن کامل

منابع من

با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید


عنوان ژورنال:
مهندسی صنایع

جلد ۴۴، شماره ۱، صفحات ۰-۰

کلمات کلیدی
the research on project scheduling has widely expanded over the last few decades. the vast majority of these research efforts focus on exact and suboptimal procedures for constructing a workable schedule assuming complete information and a static deterministic problem environment. project activities are scheduled subject to both technological precedence constraints and resource constraints mostly under the objective of minimizing the project duration. the resulting schedule serves as the baseline for the execution of the project. during execution however the project is subject to considerable uncertainty which may lead to numerous schedule disruptions. it is surprising to see that given the large amount of projects that have finished late during the last decades management still fails to quote accurate project due dates. this is problematic because virtually all organizations use their project plans not only as tools with which to manage the projects but also as a foundation to make delivery commitments to clients. therefore a vitally important purpose of project plans and effective scheduling methods is to enable organizations to estimate completion dates of the corresponding projects. a project schedule also serves as a baseline for material procurement contacts with subcontractors coordination of internal resources and corrective actions the ultimate goal which is more akin to deterministic scheduling is to make scheduling and resource allocation decisions that will allow quoting a due date that should be as low as possible. such optimizations decisions need not only be taken before the project is actually started but also scheduling and resource allocation should also be able during project execution in order protect promised dates from any sources of uncertainty that may occur. additionally if advance knowledge about the nature of the uncertainty in the project is available it is desirable that the project schedule be robust to disruptions that may arise. one of the important approaches in this issue is constructing robust project schedule. generally this approach tries to construct robust project baseline schedule by considering uncertainty in such a way that any variations cannot make disruption in it as far as possible. in this article we introduce the concept of schedule robustness and then we develop a bi objective resource constrained project scheduling model. we consider the objectives of robustness maximization along with makespan minimization. then we present a tabu search algorithm that operates on surrogate functions. this algorithm is developed in order to generate an approximate set of efficient solutions. many random project scheduling problems are generated and then solved by the algorithm. finally the efficiency of the algorithm and the robustness surrogate functions are evaluated by simulation. finally the results show efficiency of the algorithm and developed surrogate function.

میزبانی شده توسط پلتفرم ابری doprax.com

copyright © 2015-2023