Weighted Multi-Skill Resources Project Scheduling
نویسندگان
چکیده
منابع مشابه
Weighted Multi-Skill Resources Project Scheduling
In this paper, we present an extension of the classical Resource Constrained Project Scheduling Problem (RCPSP). We present a new type of resource constraints in which staff members are involved. We present a new model where staff members can have several skills with different proficiency, i.e., a staff member is able to perform more than one kind of activity as well as the time need is complet...
متن کاملModified Pareto archived evolution strategy for the multi-skill project scheduling problem with generalized precedence relations
In this research, we study the multi-skill resource-constrained project scheduling problem, where there are generalized precedence relations between project activities. Workforces are able to perform one or several skills, and their efficiency improves by repeating their skills. For this problem, a mathematical formulation has been proposed that aims to optimize project completion time, reworki...
متن کاملA Reactive Approach for the Multi-Skill Project Scheduling Problem
This paper deals with the Multi-Skill Project Scheduling Problem (MSPSP) in case of disruptions. First, the problem is defined, then a way to build a first schedule is introduced and finally the reactive approach used to repare the schedule is presented.
متن کاملLower bounds for a multi-skill project scheduling problem
This paper deals with an extension of the classical Resource Constrained Project Scheduling Problem (RCPSP). We present a new type of resource constraints in which staff members are involved. On the one hand, we focus on staff members, each of them having several skills, i.e, is able to perform more than one kind of activity. On the other hand, an activity has specific skill requirements that m...
متن کاملMulti-skill Project Scheduling Problem and Total Productive Maintenance
In this paper, we propose a multi-skill project scheduling problem model for maintenance activities organization. Preventive maintenance activities are usually planned in advance: production is stopped and all maintenance activities should be processed as fast as possible in order to restart production. Moreover, these human resource handled activities require specific skills and are subject to...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
ژورنال
عنوان ژورنال: Journal of Software Engineering and Applications
سال: 2010
ISSN: 1945-3116,1945-3124
DOI: 10.4236/jsea.2010.312131