Water management for natural channels is a frequent challenge due to the inefficient usage of water resources. The 2030 Agenda United Nations (SDG 6 sustainable development) focuses its attention on and sanitation. Sara Guerrero site, located in Mocache municipality Los Ríos province (Ecuador), has issues related access drinking water, flood control, crop irrigation that affect 4300 people 24,000 hectares. river overflows throughout rainy season (late December early May), whereas there noticeable shortage during dry season. This project aims design multiple-use earth dam Vinces River, simulating resulting flow extreme cases possible failure. Such study implies development contingency plan preservation life. It considers (i) breach analysis design, (ii) hydraulic model using ArcMap HEC-RAS software packages. includes waterproofing system controls leaks cymbal spillway, mainly raw collection. generated showed shorter failure time, higher maximum output flow. Modelling revealed four towns would be affected 31 h cases. approach offers comprehensive this community with regards control.
منابع مشابه
Investigate probability of damage of Earth dam under Near-field and Far –field earthquake : Case study Gotvand earth dam
The main goal of preset research is investigate the effects of vertical component of Near-Fault and Far-Field earthquake records on the probability of overtopping induced damage of earth dam due to the reduction of freeboard due to the settlement of dam crest. In this respect 12 different earthquake record are selected. Nonlinear dynamic analysis of earth dam is implemented with FLAC 3D using F...
متن کاملSpatial water management under alternative institutional arrangements (A case study of coastal lands of Yengejeh Dam)
Currently, water demand management and optimal operation of its resources is one ofthe most important issues in environmental economics and management. Water demandmanagement has been a concern of economic planners as a new approach in environmentaleconomics. This study aims to investigate water demand management in different productmarkets in downstream of Yengejeh Dam in Neyshabur. This is an...
متن کاملImpacts of a flash flood on drinking water quality: case study of areas most affected by the 2012 Beijing flood
In this study, we present a method for identifying sources of water pollution and their relative contributions in pollution disasters. The method uses a combination of principal component analysis and factor analysis. We carried out a case study in three rural villages close to Beijing after torrential rain on July 21, 2012. Nine water samples were analyzed for eight parameters, namely turbidit...
متن کاملtechnical and legal parameters for determination of river boundary,( case study haraz river)
چکیده با توسعه شهر نشینی و دخل و تصرف غیر مجاز در حریم رودخانه ها خسارات زیادی به رودخانه و محیط زیست اطراف آن وارده می شود. در حال حاضر بر اساس آئین نامه اصلاح شده بستر و حریم رودخانه ها، حریم کمی رودخانه که بلافاصله پس از بستر قرار می گیرد از 1 تا20 متر از منتهی الیه طرفین بستر رودخانه تعیین، که مقدار دقیق آن در هر بازه از رودخانه مشخص نیست. در کشورهای دیگر روشهای متفاوتی من جمله: درصد ریسک...
15 صفحه اولBreak fill-dam simulation using GeoStudio (case study: Safarood earth dam, Kerman)
One of the main reason of earth-dam breaks is inner erosion which is caused by washing fine soil particles and finally lead to seepage inside the dam. Seepage will decrease effective tension in the earth-dam's core and arching phenomena is occurred. More settlement of core than to shell is the consequence of arching and occurrence of cracking. In this paper, GeoStudio software based on finite e...
متن کاملذخیره در منابع من
با ذخیره ی این منبع در منابع من، دسترسی به آن را برای استفاده های بعدی آسان تر کنید
ژورنال
عنوان ژورنال: Water
سال: 2022
ISSN: ['2073-4441']
DOI: https://doi.org/10.3390/w14132029